Dummy link to fix Firefox-Bug: First child with tabindex is ignored

Camburger Straße construction process

23.10.2019

A newspaper report gave the impression that the Camburger Strasse construction site would be completed by the end of the fall vacations. However, this is not correct. The work to lay the new drinking water pipe is scheduled to be completed by mid-December. If everything goes smoothly, the work will be completed even earlier:

The rest of the process is planned as follows:

  • Line construction should be completed by the end of the 43rd calendar week. The new drinking water pipes will then be integrated.
  • By 15.11.2019: Completion of the above-ground road construction work
  • By 22.11.2019: remaining work such as restoration of ancillary areas and site clearance