Construction site information for the 33rd calendar week
Here is the current construction site report for the 33rd calendar week of 2022.
Unless otherwise stated, cyclists and pedestrians will pass the roadworks.
FINISHED CONSTRUCTION SITES
Löbichauer Straße / Karl-Liebknecht-Straße
- Gas pipes renewed, road open again
Schlegelstraße / corner of Drackendorfer Straße
- Fiber optic work completedi
NEW CONSTRUCTION SITES / ROAD CLOSURES
Forstweg
- Type: Complete closure
- Location: At house number 35a
- Duration: 15.08.2022
- Reason: Unloading activities
- Details: Pedestrians can pass the construction site safely.
Tieckstraße
- Type: Closure on one side
- Duration: 15.08. - 16.09.2022
- Reason: Installation of telecommunication lines
- Details: A one-way street will be set up for this purpose. As the construction work will also affect the entire pavement, a temporary traffic-calmed area will be installed so that pedestrians and other road users will have to move along it. Access to the adjacent apartment blocks will be made possible.
Ziegenhainer Straße
- Type: Complete closure
- Place: House number House number 7a
- Duration: 15 - 17.08.2022
- Reason: Crane installation
- Details: The adjacent one-way street will be closed so that residents/emergency and supply vehicles have access. Pedestrians and cyclists can pass the construction site safely.
EXISTING CONSTRUCTION SITES
At the planetarium
- Type: Complete closure
- Location: House number 6-8
- Duration: until 19.08.2022
- Reason: Work on the gas pipeline
- Details: A detour for motorized private traffic will be signposted on site. Pedestrians and cyclists can pass the construction site safely.
Buchenweg
- Type: Closure on one side
- Location: House number 34
- Duration: until 12.10.2022
- Reason: Construction site installation for the conversion of the adjacent school
- Details: Waiting is compulsory for vehicles meeting in the carriageway area.
Dorfstraße (Jena Wogau)
- Type: Complete closure in 3 construction phases
- Duration: until 12.08.2022
- 1st construction phase: Dorfstraße between the Wilhelm-Hauff-Weg / Dorfstraße / Im Tiefen Weg intersection
- 2nd construction phase: Dorfstraße in the area of the fork in Tiefen Weg
- 3rd construction phase: Dorfstraße from B7 to the junction with Im Tiefen Weg
- Details: Pedestrians can safely pass the closures.
Eichplatz (parking lot)
- Type: Partial closure
- Duration: until 04.12.2022
- Reason: Carrying out archaeological investigations in advance of the development of construction site A
- Details: In order to carry out the work professionally, restrictions on the parking lotare unavoidablefor a period of approx. five months. However, high priority will be given to ensuring that as many parking spaces and pathways as possible are maintained during the work. For this reason, the excavations will be carried out in three successive sections, as illustrated in the plan below.
We would also like to point out that the usual main access to Eichplatz via Kollegiengasse will not be available during this period. However, the directly adjacent temporary access road can be used asan alternative to entering the parking lot .In addition, one of the tworamps leadingfrom the parking lot to the "Neue Mitte" willno longer be available. However, the second ramp is still available without restriction.
The construction site installation, including the erection of construction fences, will begin on Friday, July 1, 2022. The legally required no parking signs for the affected areas will be posted from June 27, 2022 . The excavation work will generally be carried out from Monday to Friday from 7 a.m. to 4 p.m.
We will provide up-to-date information on the construction work and any associated restrictions or time changes on the website www.eichplatzareal.de
Felsenkellerstraße
- Type: Complete closure
- Location: House number 9 - 11
- Duration: until 19.08.2022
- Reason: extensive construction work
- Details: A detour is signposted. Pedestrians and cyclists can pass the construction site safely.
Forest road
- Type: Closure on one side
- Location: At house number 35a
- Duration: until 31.12.2022
- Reason: New construction of a residential building
Friedrich-Körner-Straße / Ernst-Pfeiffer-Straße
- Type: Complete closure
- Duration: until 17.09.2022
- Reason: Civil engineering works
- Details: During the construction period (1st construction phase), Friedrich-Körner-Straße will be fully closed. ernst-Pfeiffer-Straße will then also be fully closed. A detour will be signposted. Pedestrians can pass the construction site safely.
Gerbergasse
- Type: Closure of residents' parking lot
- Start: 25.04.2022
- Reason: Construction site installation
- Details: Alternative residents' parking spaces have been set up in Wiesenstraße from the Am Saaleufer access road. These can be used immediately.
Holzmarkt
- Type: Complete closure
- Duration: until 22.08.2022
- Reason: Maintenance work
- Details: Pedestrians and cyclists can pass the construction site safely.
Julius-Schaxel-Straße
- Type: Complete closure
- Duration: until 31.12.2022
- Reason: Road expansion incl. pipe laying
- Details: Pedestrians can pass the construction site safely. There will be 3 construction phases. Construction phases 2 + 3 will not take place until 2023.
Kochstraße
- Type: Complete closure
- Location: House number 4 to the junction with Forstweg
- Duration: until 28.10.2022
- Reason: Civil engineering works
- Details: Access/exit to the daycare center and day clinic is possible from Westbahnhofstraße
Löbderstraße
- Type: Closure on one side
- Location: between Paradiesstraße and Fischergasse
- Duration: 09 - 15.08.2022
- Reason: Civil engineering works
- Details: Closure of one lane. Traffic obstructions are to be expected.
New road surfaces
- Type: Temporary stopping restrictions and closures
- Locations: Am Jenzig, Am Hirschberge, Eichendorffweg, Feldstraße, Kirchstraße, Kötschauweg, Steingraben, Reinholdweg, Rosa-Luxemburg-Straße, Weinbergstraße
- Duration: until 31.08.2022
- Reason: Repair of the surface course
- Details: Stopping restrictions are required to carry out the work in order to clean the surfaces and carry out minor maintenance work. The very thin-layered new road surfaces can be driven on approx. 20 minutes after installation. As soon as the new road surface is passable, traffic will be reopened. The prerequisite for a rapid construction process is that all road users comply with the no-stopping regulations. In the event that the weather does not permit paving, the construction work will be postponed.
Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
- Duration: until 31.12.2022
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
Eastern Löbdergraben
- Type: Half-sided closure
- Location: between Lutherplatz and Saalstraße in the southbound direction
- Start: 20.06.2022
- Reason: Construction of the backbone network for the new university campus
- Details: The sidewalk in this area must be fully closed. Pedestrians and cyclists will be guided safely along the construction site
Otto-Schott-Straße
- Type: Full closure
- Location: At house number 28
- Duration: until 26.08.2022
- Reason: Civil engineering works
- Details: The detour is via Magdelstieg.
Schlegelstraße
- Type: Complete closure
- Location: Corner of Drackendorfer Straße
- Location: Fiber optic work
- Duration: until 12.08.2022
- Details: A detour will be signposted on site.
Thomas-Münzer-Weg
- Type: Complete closure
- Location: House number 4
- Duration: until 30.06.2023
- Reason: Construction of a residential building
- Details: The full closure will be indicated by means of planning boards from both Jägerbergstraße and Max-Gräfe-Gasse. A wide detour must be taken around the closed area. Pedestrians and cyclists can pass the construction site safely.
Change to the one-way street layout in Unterdorfstraße and Wöllnitzer Oberwe
- Type: Complete closure
- Location: Unterdorfstraße 2
- Duration: until 31.12.2022
- Reason: Construction work
- Details: The one-way street layout will be changed in the above-mentioned streets. In Unterdorfstraße, it will then be possible to drive out of the city and in Wöllnitzer Oberweg, it will be possible to drive into the city. Cyclists will be able to ride against the one-way street in Wöllnitzer Oberweg. Signage will be erected at the start of the construction work to raise awareness among road users.
Weigelstraße
- Type: Complete closure
- Location: between Fürstengraben and Jenergasse
- Duration: until 29.08.2022
- Reason: Civil engineering works
- Details: The detour is via the Eichplatz parking lot and will be signposted. Pedestrians can pass the construction site safely.
Wenigenjenaer Ufer
- Type: Complete closure
- Location: At house number 17 b to the junction with Tümplingstraße
- Duration: until 30.09.2022
- Reason: Renewal of the combined sewer
- Details: The construction work will be divided into 2 construction phases. A detour will be signposted.
- 2nd construction phase: House number 15-17 b
- 1st construction phase: Tümplingstraße up to house number 15
Wiesenstraße
- Type: Complete closure
- Location: House number 30 to the height of the Schinner car dealership
- Duration: 08 - 26.08.2022
- Reason: Renewal of the surface course
- Details: The construction work is to be carried out in 2 construction phases (each as a full closure). The 1st construction phase from 08.08.2022 will take place out of town. Traffic will be diverted via Löbstedter Straße and Am Alten Gaswerk. Pedestrians and cyclists will be widely diverted.
Wiesenstraße
- Type: Temporary closure
- Location: Junction with Am Anger up to the level of Wiesencenter
- Duration: until 16.09.2022
- Reason: Civil engineering works
- Details: From 25.07.2022 to 19.08.2022,the civil engineering work willcontinue in the direction of Am Anger Hnr. 22 will be continued. The pavement must be fully closed for this. Pedestrians will be guided past the construction site by detour signs.
Motorized private traffic is also affected. At the Am Anger / Lutherplatz junction, there will be a ban on left turns. Road users wishing to turn left from Am Eisenbahndamm via Am Anger to Lutherplatz and on towards Fürstengraben will not be able to do so during the above-mentioned period. The reason for this is the removal of a lane. It will only be possible to go straight on in the direction of Am Anger or turn left in the direction of Wiesenstraße.
Ziegenhainer Straße
- Type: Complete closure
- Location: House number 7a
- Duration: until 31.12.2022
- Reason: New house construction
- Details: Properties in the direction of Burgweg can be reached. Pedestrians can pass the construction site safely.
ANNOUNCEMENTS
Carolinenstraße
- Type: Complete closure
- Duration: 22.08. - 14.10.2022
- Reason: Pavement renovation
- Details: The construction work will be divided into several construction phases so that access for residents/rescue and supply services is guaranteed. A detour will be signposted on site. Pedestrians and cyclists can pass the construction site safely.
Complete closure of Oberaue from the southern access road to the main access road at Stadtrodaer Straße
- Type: Complete closure
- Duration : 22.08. - 31.12.2022
- Fundamental expansion of the access road
Expansion and widening of the main cycle path connection - Detour: A designated detour route will be set up for cyclists heading into and out of the city. The cycle routes run via Wöllnitzer Straße and Burgauer Weg.
- Details: The work will take place from 22.08.2022 behind the southern access road to the stadium. From 29.08.2022, there will then be restrictions for bathers when accessing the Südbad/Schleichersee and beach bar as well as for adjacent sports facility users. The facilities will be accessible from the main stadium access road via a temporary footpath. This walkway can only be used by pedestrians - cyclists must dismount.
Guests of the Schleichersee and the adjacent sports facilities as well as the traffic school with cars can use the parking lot in the Oberaue directly next to the main access road. This is only not possible when FC Carl Zeiss Jena is playing at home. A planning board will be set up at the main entrance to the Oberaue so that road users are informed.
To the Ziskauer Valley (Lützeroda)
- Type: Complete closure
- Duration: 29.08. - 21.12.2022
- Reason: Civil engineering works
- Details: A detour will be signposted on site.