Construction site report 12th week (21. - 27.03.2022)
Here is the current roadworks report for the 12th calendar week of 2022.
Unless otherwise indicated, cyclists and passers-by will pass the roadworks.
New construction sites
Blochmannstraße
- Type: Complete closure
- Duration: 21.03. - 17.06.2022
- Reason: Renewal of the supply lines
- Details: A detour will be set up on site.
Eichplatz
- Type: Partial closure
- Duration: Monday, 21.03.2022, 17.00 - 22.00 hrs
- Reason: Demonstration
Finished construction sites
-
None
Existing construction sites
"Bridge in front of the Neutor"
- Type: Complete closure
- Duration: until 30.04.2022
- Reason: New construction of the bridge
- Traffic will be diverted as follows:
- out of town via Erbertstraße - Ernst-Haeckel-Straße
- into the city via Ernst-Haeckel-Straße - Schillerstraße - Teichgraben
- Details: Underpass to Paradies fully closed - detour signposted
Brändströmstraße and Gabelsbergerstraße
- Type: Full closure
- Location: Gabelsbergerstraße and Brändströmstraße intersection area
- Duration: until 17.06.2022
- Reason: Renewal of the sewage pipes
- Details: Brändströmstraße Hnr. 13 to 20 - coming fromKarl-Günther-Straße- will be signposted as a dead end. The lower part of Brändströmstraße is requiredas a storage area. Pedestrians can pass the construction site safely.
Buchenweg
- Type: Half-sided closure
- Location: House number 34
- Duration: until 12.07.2022
- Reason: Construction site installation for the conversion of the adjacent school
- Details: Waiting is compulsory for vehicles meeting in the carriageway area.
Dornburger Straße
- Type: Complete closure
- Location: from the junction with Friedrich-Wolf-Straße to the junction with An der Eule
- Duration: until 30.06.2022
- Reason: Civil engineering works
- Details: A detour will be signposted. Pedestrians can pass the construction site safely.
Emil-Wölk-Straße (bus stop)
- Type: Closure on one side
- Location: Karl-Marx-Allee at Emil-Wölk-Straße (towards the traffic circle)
- Duration: until 31.03.2022
- Reason: New construction of bus stop
- Details: Traffic will be diverted via Stauffenbergstraße.
Hornstraße
- Type: Complete closure
- Duration: until 22.04.2022
- Reason: Renovation of the "Dornröschen" daycare center
- Details: Pedestrians can pass.
Karl-Liebknecht-Straße
- Type: Complete closure
- Place: House number 34 - 44
- Duration: until 01.04.2022
- Reason: Civil engineering works
- Details: Pedestrians will be diverted to the opposite sidewalk.
Kollegiengasse
- Type: New installation of the full closure
- Location: between Nonnenplan, Löbderstraße and along the Neue Mitte
- Duration: until 25.05.2022
- Reason: Civil engineering works
- Details: A detour is signposted. Access to Eichplatz is possible.
Kunitzer Straße - Jenzigweg underpass
- Type: Complete closure
- Duration: until 29.04.2022
- Reason: Laying of supply lines for the adjacent "Erlenhöfe" construction project
- Details: A detour for pedestrians is signposted.
Oberaue
- Type: Complete closure
- Location: House number 20 to the Lichtenhainer bridge
- Duration: until 31.03.2022
- Reason: Work on the high-pressure gas pipeline
- Details: The running hall and adjacent sports fields can be accessed. Access in the direction of Lichtenhainer Brücke is not possible. A corresponding detour for pedestrians and cyclists is signposted.
-
We would like to take this opportunity to clearly point out that moving or removing traffic signs and traffic facilities constitutes a dangerous interference with road traffic. The above-mentioned area is controlled. Traffic signs (e.g. detour signs) are for orientation purposes and must remain in place.
Schützenhofstraße
- Type: Half-sided closure
- Location: House number 74-78
- Duration: until 01.07.2022
- Reason: Construction site installation for the conversion of the adjacent apartment block
- Details: Pedestrians can pass safely.
Announcements
Dorfstraße (Jena Wogau)
- Type: Complete closure in 3 construction phases
- Duration: 28.03. - 29.07.2022
- Reason: Crane installation
- 1st construction phase: Dorfstraße between the Wilhelm-Hauff-Weg / Dorfstraße / Im Tiefen Weg intersection
- 2nd construction phase: Dorfstraße in the area of the fork in Tiefen Weg
- 3rd construction phase: Dorfstraße from B7 to the junction with Im Tiefen Weg
Winzerlaer Straße
- Type: Complete closure
- Duration: 29.03.2022 from 6:00 am to 31.03.2022, 6:00 pm
- Reason: Crane installation
- A detour is signposted as follows:
- out of town via Hermann-Löns-Straße and Rudolstädter Straße
- into the city via Rudolstädter Straße - Kahlaische Straße - Ernst-Haeckel-Straße - Westbahnhofstraße - Magdelstieg and Tatzendpromenade