Construction site report 17.KW (25.04. - 01.05.2022)

22.04.2022

Here is the current roadworks report for the 17th calendar week of 2022.

Unless otherwise stated, cyclists and passers-by will pass the roadworks.

New construction site

Bachstraße

  • Type: Complete closure
  • Location: Height Hnr. 39
  • Start: 01.05.2022, 8:00 - 14:00 o'clock
  • Reason: DGB rally
  • Details: Johannisplatz will also be closed until the junction with Leutragraben.Pedestrians can safely passthe closed area.

Gerbergasse

  • Type: Closure of residents' parking lot
  • Start: 25.04.2022
  • Reason: Construction site installation
  • Details: Alternative residents' parking spaces have been set up in Wiesenstraße from the Am Saaleufer access road. These can be used immediately.

Hornstraße

  • Type: Complete closure
  • Start: 25.04.2022 - 13.05.2022
  • Reason: Work on the road and footpath
  • Details: Pedestrians will have a sidewalk available for safe passage.

Sophienstrasse

  • Type: Complete closure
  • Location: Junction with Käthe-Kollwitz-Straße to junction with Theo-Neubauer-Straße
  • Duration: 01.05.2022, 10:00 - 17:00 hrs
  • Reason: Street festival
  • Details: The intersection ofArvid-Harnack-Straße is excluded from the closure in west-east direction. The St.-Jakob-Straße intersection will also be closed and secured with barrier beacons and barriers. Vehicles entering and exiting the cul-de-sac in St.-Jakob-Straße will be allowed to enter and exit .Pedestrians can safely pass throughtherestrictedarea.

Stadtrodaer Straße

  • Type: Closure
  • Location: between Seidelplatz and the Wöllnitz junction
  • Duration: 01.05.2022, 7:00 am - 6:00 pm
  • Reason: 32nd Duathlon
  • Details: Motorized traffic will be diverted past the event. One lane will be available for both inbound and outbound traffic.

Finished construction sites

Hornstrasse

  • Renovation of the "Dornröschen" daycare center has been completed.

Max-Großmann-Straße

  • Civil engineering work has been completed.

Nollendorfer Platz / Dornburger Straße

  • Adjustment of the points control system and renovation of the track bed have been completed.

Oberaue

  • Work on the high-pressure gas pipeline has been completed.

Rautal

  • Civil engineering work has been completed.

Schillerstraße / Goethe-Galerie main entrance

  • Civil engineering work has been completed.

Existing construction sites

Traffic circle
Alexander-Puschkin-Platz

  • Type: Complete closure
  • Duration: until 06.05.2022
  • Reason: Reconstruction of the traffic circle
  • Details: A detour will be signposted. It is advisable to drive around the restricted area.

Blochmannstraße

  • Type: Complete closure
  • Duration: until 17.06.2022
  • Reason: Renewal of the supply lines
  • Details: A detour will be set up on site.

Brändströmstraße and Gabelsbergerstraße

  • Type: Complete closure
  • Location: Gabelsbergerstraße and Brändströmstraße intersection area
  • Duration: until 17.06.2022
  • Reason: Replacement of the sewer pipes
  • Details: Brändströmstraße Hnr. 13 to 20 - coming from Karl-Günther-Straße - will be signposted as a dead end. The lower part of Brändströmstraße is required as a storage area. Pedestrians can pass the construction site safely.

"Bridge in front of the Neutor"

  • Type: Complete closure
  • Duration: until 30.04.2022
  • Reason: New construction of the bridge
  • Traffic will be diverted as follows:
    • out of town via Erbertstraße - Ernst-Haeckel-Straße
    • into the city via Ernst-Haeckel-Straße - Schillerstraße - Teichgraben
  • Details: The footpath below the railroad, which leads to Paradis, is currently open again. However, there may be temporary full closures as construction work continues.

Buchenweg

  • Type: Half-sided closure
  • Location: House number 34
  • Duration: until 12.07.2022
  • Reason: Construction site installation for the conversion of the adjacent school
  • Details: Waiting is compulsory for vehicles meeting in the carriageway area.

Dorfstraße (Jena Wogau)

  • Type: Complete closure in 3 construction phases
  • Duration: until 29.07.2022
  • 1st construction phase: Dorfstraße between the Wilhelm-Hauff-Weg / Dorfstraße / Im Tiefen Weg junction
  • 2nd construction phase: Dorfstraße in the area of the fork in Tiefen Weg
  • 3rd construction phase: Dorfstraße from B7 to the junction with Im Tiefen Weg
  • Pedestrians can pass the closures safely.

Dornburger Straße

  • Type: Complete closure
  • Location: from the junction with Friedrich-Wolf-Straße to the junction with An der Eule
  • Duration: until 30.06.2022
  • Reason: Civil engineering works
  • Details: A detour will be signposted. Pedestrians can pass the construction site safely.

Karl-Liebknecht-Straße

  • Type: Complete closure
  • Location: House number 34 - 44
  • Duration: until 30.04.2022
  • Reason: Civil engineering works
  • Details: Pedestrians will be diverted to the opposite sidewalk.

Karl-Marx-Allee

  • Type: Complete closure
  • Location: western part of Karl-Marx-Allee incl. traffic circle
  • Start: until 29.04.2022
  • Reason: Road renewal
  • Details: A detour will be signposted on site. Replacement stops will be set up in Stauffenbergstraße.

Kollegiengasse

  • Type: New installation of the full closure
  • Location:between Nonnenplan and Neue Mitte
  • Duration: until 29.04.2022
  • Reason: Civil engineering works
  • Details: A detour is signposted. Access to Eichplatz will be possible. Following this full closure, civil engineering work will be carried out along the new center. This may result in minor temporary restrictions on the PP Eichplatz. The overall construction project is scheduled for completion on 25.05.2022.

Kunitzer Straße - Jenzigweg underpass

  • Type: Complete closure
  • Duration: until 29.04.2022
  • Reason: Laying of supply lines for the adjacent "Erlenhöfe" construction project
  • Details: A detour for pedestrians is signposted.

Oberaue

  • Type: Complete closure
  • Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
  • Start: until 31.03.2023
  • Reason: Work on the stadium grandstand
  • Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists will be signposted.

Schützenhofstraße

  • Type: Closure on one side
  • Location: House number 74-78
  • Duration: until 01.07.2022
  • Reason: Construction site installation for the conversion of the adjacent apartment block
  • Details: Pedestrians can pass safely.

Ziegenhainer Straße

  • Type: Complete closure
  • Location: House number 7a
  • Start: until 31.12.2022
  • Reason: New house construction
  • Details: Access to adjacent properties towards Burgweg is possible. Passers-by can pass the construction site.

Announcements

Change to the one-way street layout in Unterdorfstraße and Wöllnitzer Oberweg

  • Type: Complete closure
  • Location: Unterdorfstraße 2
  • Duration: 16.05. - 31.12.2022
  • Reason: Construction work
  • Details: The one-way street layout will be changed in the above-mentioned streets. In Unterdorfstraße, it will then be possible to drive out of the city and in Wöllnitzer Oberweg, it will be possible to drive into the city. Cyclists will be able to ride against the one-way street in Wöllnitzer Oberweg. Signage will be put up at the start of the project to raise road users' awareness.