The construction site report for the 19th calendar week of 2019
Finished construction sites
- Moritz-von-Rohr-Straße
Half-sided closure ended - Beutnitzer Straße 1
The street is no longer a dead end - Total closure of Saarbrücker Straße 28
Road fully passable again - Half-sided closure of Lutherstraße 191
House connection is in place, no more obstructions
New closures
- Full closure of Otto-Schott-Straße
Construction work on Otto-Schott-Straße will begin on Monday, May 8. Asphalt work will be carried out between the JenaPharm exit and Berthold-Koch-Platz. The work will be divided into two sections. The first section, which will last until May 15, begins at the JenaPharm exit and ends shortly after the corner of Schleidenstraße and Carl-Pulfrich-Straße.
For drivers, this means
From Tatzendpromenade:
Otto-Schott-Straße only free as far as OkenstraßeComing out of town:
Otto-Schott-Straße only free as far as Kronfeldstraße - Complete closure of Drosselstraße
From 06.05.2019 to 29.05.2019, Drosselstraße between Jenaprießnitzer Straße and Steingraben will be closed to vehicle traffic. The closure is necessary due to the reconstruction of the gas pipes in Drosselstraße.
During the closure, one-way traffic on Steingraben will be suspended. Resident traffic in Steingraben will be regulated by traffic lights at the junction with Karl-Liebknecht-Straße. - Jena Spring Market
Due to the Jena Spring Market, the town hall parking lot and Eichplatz will be closed for parking from May 6, 2019 to May 20, 2019. The e-charging station on Eichplatz can still be used. Access is from Kollegiengasse. During the Jena Spring Market, the delivery time for the Altstadt pedestrian zone will be limited to the time between 06:00 and 12:00. - Am Volksbad
From 06.05.2019 until 28.06.2019, Am Volksbad will be closed on one side and will only be accessible from Grietgasse in the direction of Knebelstraße. The closure is necessary for the construction of a footpath including ancillary facilities at the bus station. The detour is signposted. - Complete closure of Semmelweisstraße
From 06.05.2019 to 09.05.2019, the Semmelweisstraße / Wilhelm-Külz-Straße junction will be closed to vehicle traffic in order to be able to lay the cables in the road space of the junction. A detour via the adjacent road network will be signposted.
Existing locks
- Complete closure of Karl-Liebknecht-Straße
Stadtwerke will be laying a new combined sewer in the area between Brändströmstraße and Pestalozzistraße until around 31.05.2019. During this time, Karl-Liebknecht-Straße will be completely closed to vehicle traffic in the construction area.
completely closed to vehicle traffic.Traffic will be diverted in both directions via Jenzigweg and Wiesenstraße to the Anger junction. The traffic light control at the Anger junction is to be optimized. However, residents can also bypass the roadworks via Am Steinborn and Löbichauer Straße. Temporary stopping restrictions will be put in place along this route to support traffic flow
- Closure of Naumburger Straße / Rautal
The Naumburger Straße / Am Steinbach intersection is fully closed. The large-scale detour is via Brückenstraße - Wiesenstraße - Am Anger and back.Despite the barriers in Brückenstraße: Please do not attempt to drive through the residential area! Public and school buses drive through the small streets. "Creeping traffic" would massively obstruct local traffic there. In addition, the sidewalks are partially separated from the carriageway - the safety of school routes has top priority.
We would like to thank all considerate drivers!
-
Complete closure of Lichtenhainer Oberweg between the Carl-Zeiss-Promenade junction and the Döbereinerstrasse junction
A full road closure will be implemented in the above-mentioned area from 01.04.2019 to 28.06.2019. During the closure period, traffic will be diverted via the adjacent streets Phillip-Müller-Straße; Döbereinerstraße; Friedrich-Körner-Straße. The detour is signposted. -
Construction work on Camburger Straße
The construction work started in 2018 to lay drinking water pipes in Camburger Straße is now continuing and is scheduled to last until the end of June. During the construction period, road traffic in the direction of the city center will remain on Camburger Straße. As last year, northbound traffic will be routed back to Camburger Straße via Spitzweidenweg and Scharnhorststraße. -
Complete closure of Schillstraße 1
Schillstraße will be closed from 08.04.2019 to 31.05.2019 because the sewer and house connections have to be renewed in this area. Road traffic will be diverted locally and the detour will be signposted. -
Full closure of Mittelstraße
From 08.04.2019 to 30.08.2019, the sewer will be renewed in Mittelstraße between Otto-Schott-Straße and Kronfeldstraße. This section of road will be completely closed to vehicle trafficfor the milling of the road surface . Afterwards, a section-by-section full closure in the immediate work area will be necessary. It is possible to drive around the construction site via the adjacent roads. - Narrowing of Am Eisenbahndamm road
In the period from 25.03.2019 to 26.07.2019, a drinking water pipeline will be laid through the railroad embankment between Landveste and Straße am Eisenbahndamm on behalf of the municipal utilities. During this construction work, the cycle/walking path will be closed in the area of the construction site at Landveste and rerouted in the area of Landveste. There will also be a temporary narrowing of the road Am Eisenbahndamm, especially at times when traffic is lighter, as one of the two left-turn lanes in the direction of Paradiesbrücke (Stadtrodaer Straße) will have to be shortened slightly.
- Traffic obstructions at the Mühlenstraße / Hermann-Löns-Straße junction
Construction work has currently begun in the intersection area and will continue until 26.04.2019. During the construction work in the intersection area, electrical cables are being laid in the sidewalk area of the intersection. During the work, traffic will have to be controlled by traffic lights. This will result in traffic obstructions on Hermann-Löns-Straße.
- Complete closure of Rautalstraße
From 25.03.2019, Rautalstraße between Kuithanstraße and Ottogerd-Mühlmann-Straße will be closed to vehicle traffic. The detour will be via Kuithanstraße, Zitzmann-Straße, Straße and Ottogerd-Mühlmann-Straße or G.-Neumann-Straße. The closure is expected to last until mid-May 2019. After that, the Rautal area between Ottogerd-Mühlmann-Straße and Jägerbergstraße will be closed and traffic will be diverted via Closewitzer Straße. This section is scheduled to be reopened to traffic on 05.07.2019.
During the closure period, a new drinking water pipeline will be laid in Rautal.
In the fall of this year, this new drinking water pipeline is to be laid further along the Rautal to the end of Jena in the direction of Closewitz.
- Maria-Pawlowna-Straße
In the period from 11.03.2019 to 07.06.2019, the road will be closed to vehicle traffic due to construction work on the district heating pipeline. Traffic between Naumburger Straße and Schreckenbachweg or Am Rosenhang will be diverted in both directions via Flurweg.
- Max-Wien-Platz
The property at Philosophenweg 26 is being built on. For this reason, traffic space restrictions are necessary in the area where Kritzegraben joins Philosophenweg. In order not to divert traffic, a traffic light system will regulate traffic at this junction. The traffic restriction will end in the middle of 2019
- Closure of Marktstraße in Lobeda-Altstadt
Construction work for the further expansion of Marktstraße between Marktplatz and Nikolaus-Theiner-Straße and further via Lobdeburgweg between Stadtgraben and Spitzbergstraße until 27.09.2019 - road closures in sections.
- Complete closure of Saarbrücker Straße 28
From 23.04.2019 to 29.04.2019, Saarbrücker Straße will be closed to vehicle traffic at no. 28. Saarbrücker Straße can only be accessed from the direction of St.-Wendel-Stieg as well as from the direction of Völklinger Stieg as a dead end without the possibility of turning.
- Road closure Stifterstraße
Due to the laying of a new drinking water pipe, Stifterstraße will be closed to vehicle traffic from 23.04.2019 to 31.07.2019. The construction work will be carried out in two phases in order to minimize traffic disruptions for residents. - Full closure of Rautalstraße
Since 25.03.2019, Rautalstraße between Kuithanstraße and Ottogerd-Mühlmann-Straße has been closed to vehicle traffic. The detour was made via Kuithanstraße, Zitzmann-Straße, Straße and Ottogerd-Mühlmann-Straße or G.-Neumann-Straße.
From 25.04.2019 to 29.05.2019, the Rautal area between Ottogerd-Mühlmann-Straße and Jägerbergstraße will also be closed and traffic will be diverted via Closewitzer Straße.