Construction site report 20th week (16.-22.05.2022)
Here is the current roadworks report for the 20th calendar week of 2022.
Unless otherwise stated, cyclists and pedestrians will pass the roadworks.
New construction site
Am Steinbach level crossing
- Type: Traffic obstruction
- Duration: 17 - 18.05.2022
- Reason: Road marking work
- Details: Traffic obstructions may occur at certain points.
Camburger Straße
- Type: Half-sided closure
- Location: At house number 65
- Duration: 17 - 18.05.2022
- Reason: Establishment of a construction site access road
- Details: Traffic jams are to be expected. Pedestrians and cyclists will be diverted.
Dornburger Straße (out of town)
- Type: Complete closure
- Location: At the Nordschule stop
- Start: 16 - 25.05.2022
- Reason: Repair work in the track area
- Details: Traffic will be diverted via Camburger Straße. Access from the direction of Nollendorfer Hof is possible up to Dornburger Straße 26. Pedestrians can pass the construction site safely.
Felsenkellerstraße
- Type: Complete closure
- Location: House number 9 -11
- Duration: 18.05. - 19.08.2022
- Reason: extensive construction work
- Details: A detour will be signposted. Pedestrians and cyclists can pass the construction site safely.
Company run 2022
- Type: Restrictions see image
- Duration: 18.05.2022 , 18:30 - 20:30
- Reason: Event
- Details: Traffic obstructions are to be expected in Jena Burgau.
Juri-Gagarin-Straße
- Type: Full closure
- Location: behind the junction with Naumburger Straße
- Start: 18 - 31.05.2022
- Reason: Civil engineering works
- Details: Pedestrians can pass the construction site safely. The detour is via Kreuzgasse - Florian-Geyer-Weg.
Magdelstieg
- Type: Complete closure
- Location: At house number 117
- Duration: 17.05. - 16.06.2022
- Reason: Civil engineering works
- Details: A detour will be signposted. Pedestrians and cyclists can pass the construction site safely.
Change to the one-way street layout in Unterdorfstraße and Wöllnitzer Oberweg
- Type: Complete closure
- Location: Unterdorfstraße 2
- Duration: 16.05. - 31.12.2022
- Reason: Construction work
- Details: The one-way street layout will be changed in the above-mentioned streets. In Unterdorfstraße, it will then be possible to drive out of the city and in Wöllnitzer Oberweg, it will be possible to drive into the city. Cyclists will be able to ride against the one-way traffic in Wöllnitzer Oberweg. Signage will be erected at the start of the construction work to raise road users' awareness.
Completed roadworks
Camburger Straße
- Construction work on an electronic billboard has been completed.
Fischergasse
- Damage has been repaired.
Wöllnitz pedestrian bridge
- The floor covering has been replaced.
Existing construction sites
Am Steinborn
- Type: Half-sided closure
- Location: House number 35
- Duration: until 27.05.2022
- Reason: Reconstruction of apartment block
- Details: Pedestrians can pass the closure.
Blochmannstraße
- Type: Complete closure
- Duration: until 17.06.2022
- Reason: Renewal of the supply lines
- Details: A detour will be set up on site.
Brändströmstraße and Gabelsbergerstraße
- Type: Complete closure
- Location: Gabelsbergerstraße and Brändströmstraße intersection area
- Duration: until 17.06.2022
- Reason: Renewal of the sewer pipes
- Details: Brändströmstraße Hnr. 13 to 20 - coming from Karl-Günther-Straße - will be signposted as a dead end. The lower part of Brändströmstraße is required as a storage area. Pedestrians can pass the construction site safely.
Buchenweg
- Type: Half-sided closure
- Location: House number 34
- Duration: until 12.07.2022
- Reason: Construction site installation for the conversion of the adjacent school
- Details: Waiting is compulsory for vehicles meeting in the carriageway area.
Dorfstraße (Jena Wogau)
- Type: Complete closure in 3 construction phases
- Duration: until 29.07.2022
- 1st construction phase: Dorfstraße between the Wilhelm-Hauff-Weg / Dorfstraße / Im Tiefen Weg junction
- 2nd construction phase: Dorfstraße in the area of the fork in Tiefen Weg
- 3rd construction phase: Dorfstraße from B7 to the junction with Im Tiefen Weg
- Details: Pedestrians can pass the closures safely.
Dornburger Straße
- Type: Complete closure
- Location: from the junction with Friedrich-Wolf-Straße to the junction with An der Eule
- Duration: until 30.06.2022
- Reason: Civil engineering works
- Details: A detour will be signposted. Pedestrians can pass the construction site safely.
Gerbergasse
- Type: Closure of residents' parking lot
- Start: 25.04.2022
- Reason: Construction site installation
- Details: Alternative residents' parking spaces have been set up in Wiesenstraße from the Am Saaleufer access road. These can be used immediately.
Hornstraße
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
- Start: until 31.05.2022
- Reason: Work on the road and footpath
- Details: A footpath is available for pedestrians to pass safely.
Hufelandweg
- Type: Complete closure
- Location: in the direction of Dornburger Str. between Von-Hase-Weg and Thomas-Mann-Str.
- Probable duration: until 20.05.22
- Reason: Accident
Kochstraße
- Type: Complete closure
- Location: House number 4 to the junction with Forstweg
- Duration: until 31.07.2022
- Reason: Civil engineering works
- Details: Access to the daycare center and day clinic is possible from Westbahnhofstraße
Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
- Start: until 31.03.2023
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists will be signposted.
Schützenhofstraße
- Type: Closure on one side
- Location: House number 74-78
- Duration: until 01.07.2022
- Reason: Construction site installation for the conversion of the adjacent apartment block
- Details: Pedestrians can pass safely.
Weigelstraße
- Type: Half-sided closure
- Location: in the direction of Rathausgasse
- Probable duration: until 20.05.22
Ziegenhainer Straße
- Type: Full closure
- Place: House number 7a
- Start: until 31.12.2022
- Reason: New house construction
- Details: Access to adjacent properties towards Burgweg is possible. Passers-by can pass the construction site.
Announcements
Lerchenstieg
- Type: Complete closure
- Location: Junction Am Steinborn to Hnr. 23
- Start: 30.05. - 03.06.2022
- Reason: Road surface renovation
- Details: Access and exit restrictions are to be expected. Access to the adjacent properties will be possible during certain time windows after consultation with the construction company.
Otto-Schott-Straße
- Type: Complete closure
- Location: At house number 28
- Start: 23.05. - 10.06.2022
- Reason: Civil engineering works
- Details: A detour will be signposted. Pedestrians and cyclists can pass the construction site safely.