Construction site report 2nd week (09. - 15.01.2022)
Here is the current roadworks report for the 2nd calendar week of 2023.
Unless otherwise stated, you can walk or cycle past the construction sites.
COMPLETED CONSTRUCTION SITES
Ziegenhainer Straße 7a
- Complete closure lifted
NEW CONSTRUCTION SITES / CLOSURES
None
EXISTING ROADWORKS
Buchenweg
- Type: Half-sided closure
- Location: House number 34
- Duration: until 13.01.2023
- Reason: Construction site installation for the conversion of the adjacent school
- Details: Waiting is compulsory for vehicles meeting in the carriageway area.
Julius-Schaxel-Straße
- Type: Complete closure
- Duration: until 31.03.2023
- Reason: Road expansion incl. pipe laying
- Details: The construction site can be passed on foot. There will be 3 construction phases.
Lessingstraße
- Type: Complete closure
- Location: House number 1-6
- Duration: until 28.02.2023
- Reason: Laying of district heating pipe
- Details: The area can be passed on foot and by bike
- Addition: During the winter break (start 19.12.2022 - end not yet known), Lessingstraße will be passable by one-way traffic.
Lobeda-Altstadt - Neulobeda - Drackendorf
- Type: Restrictions
- Duration: until 24.02.2023
- Reason: Civil engineering work for laying fiber optic cable
Max-Gräfe-Gasse
- Type: Partial closure
- Location: Corner of Kreuzgasse
- Duration: until 31.03.2023
- Reason: Construction site installation for house conversion
- Details: The construction site can be passed.
Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
- Duration: until 31.03.2023
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
Thomas-Münzer-Weg
- Type: Complete closure
- Location: House number 4
- Duration: until 30.06.2023
- Reason: Construction of a residential building
- Details: The full closure is indicated by means of planning boards from both Jägerbergstraße and Max-Gräfe-Gasse. The restricted area must be driven around extensively. The construction site can be safely passed on foot and by bike.
Wöllnitz and Ammerbach
- Type: temporary restrictions
- Duration: until approx. 28.02.2023
- Reason: Civil engineering work for laying fiber optic cable
Zum Ziskauer Tal (Lützeroda)
- Type: Complete closure
- Duration: until 28.04.2023
- Reason : Civil engineering works (sewage; drinking water)
- Details: A detour will be signposted on site.
ANNOUNCEMENT
None