The construction site report for the 50th calendar week (11 - 17.12.2023)
Here is the current roadworks report for the 50th calendar week (11 - 17.12.2023)
Unless otherwise stated, you can walk or cycle past the roadworks.
COMPLETED CONSTRUCTION SITES
At the Erlkönig
- Installation of the transformer station is complete.
Erlanger Allee - cycle path connection between Lobeda-Ost and Lobeda-West
- Construction of a cycle path connection has been completed.
Wiesenbrücke bridge
- Bridge inspection has been completed.
NEW CONSTRUCTION SITES / CLOSURES
None
EXISTING CONSTRUCTION SITES
Artur-Becker-Straße
- Type: Complete closure
- Location: House number 23
- Duration: until 15.12.2023
- Reason: Replacement of the drinking water pipe
- Details: A detour to the animal shelter will be signposted on site. The construction site can be passed safely on foot.
B7
- Type: Closure on one side
- Location: between the junction Vor der Gembdenmühle and the Jena town entrance sign
- Duration: until 21.12.2023
- Reason: Road surface renovation incl. sidewalk construction and fiber optic expansion
- Details: Traffic will be guided safely past the construction site by means of a mobile traffic light system
Dammstrasse
- Location: Magnus-Poser-Straße to Schenkstraße (1st construction phase)
- Type: Complete closure
- Duration: until 30.05.2024
- Reason: Laying of pipes and renewal of the road surface
- Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.
1st construction phase: Magnus-Poser-Straße to Schenkstraße
2nd construction phase: Schenkstraße to Charlottenstraße
Drackendorf (Am Goethepark and Am König)
- Type: Temporary restrictions
- Duration: until 22.12.2023
- Reason: Civil engineering work for laying fiber optic cables
Ernst-Pfeiffer-Straße
- Type: Complete closure
- Duration: until 22.12.2023
- Reason: Surface course + boarding installation
- Details: The construction site can be passed safely on foot
Grenzstraße
- Type: Closure on one side
- Location: At house number 2-4
- Duration: until 01.03.2024
- Reason: Construction of an apartment building
- Details: Pedestrians will be guided safely past the construction site with the help of an emergency pedestrian route
Holzmarkt
- Type: Complete closure
- Location: At the "Roter Hirsch" inn
- Start: 02.12.2023
- Reason: Damage to the drinking water pipe repaired, investigation of cavities/ washouts still pending.
- Details: The road remains closed to traffic. The buses of the lines 10, 11 and 12 of the Jenaer Nahverkehr continue to drive a detour. Delays are to be expected.
Kunitz
- Type: Temporary restrictions
- Duration: probably until 20.12.2023
- Reason: Continuation of civil engineering work for fiber optic expansion
- Details: There will be restrictions in the areas of Am Mönchsberge, Am Wiesenbach, Am Spielberg, Vor dem Obertore, Kirchstraße, Lange Straße, Blumenröschenweg and Bachgasse.
Lobeda Old Town
- Type: Temporary half-side closure + sidewalk closure
- Duration: until 29.12.2023
- Reason: Civil engineering work for laying fiber optic cable
- Details: The construction site can be passed safely on foot.
Lobeda East and Illmnitz
- Type: Temporary half-sided closure + footpath closure
- Duration: until 22.12.2023
- Reason: Civil engineering work for laying fiber optic cable
- Details: The construction site can be passed safely on foot.
Löbichauer Straße
- Type: Complete road closure
- Location: Lower Löbichauer Straße (Karl-Liebknecht-Straße to Eschenplatz)
- Duration: until 31.12.2023
- Reason: Civil engineering works
- Details: The construction site can be passed safely on foot.
Münchenrodaer Grund (corner of Am Mühlberg)
- Type: Closure on one side
- Duration: until 20.12.2023
- Reason: Rock stabilization work
- Details: The closed area is located behind the junction Am Mühlberg upwards in the direction of Schottplatz.
2x Naumburger Straße
- Type: Half-sided closure
- Duration: until 31.01.2024
- Reason: Conversion of the streetcar stop + installation of track replacement
- Details: During the construction period, a one-way street will be installed from the Zitzmannstraße junction to Altenburger Straße. The one-way street is passable in the direction of the city center. The construction site can be passed safely on foot.
- Type: Half-sided closure
- Location: At house number 161
- Duration: until 20.12.2023
- Reason: Supply line work
- Details: Pedestrians will be guided safely past the construction site in the sidewalk area with the help of a pedestrian emergency route. Meanwhile, traffic will move on both sides.
Nollendorfer Strasse
- Type: Complete closure
- Location: between Thomas-Mann-Straße and Dornburger Straße
- Duration: until 30.05.2024
- Reason: Major road renovation
2x Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
- Duration: until 23.12.2023
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
- Type: Half-sided closure
- Location: From the main stadium access road to Roland-Ducke-Weg
- Duration: until 22.12.2023
- Reason: Expansion of the road and ancillary facilities
- Details: The construction site can be passed, but obstructions are to be expected. Cyclists can bypass the construction site safely and quickly. A detour has been set up and signposted for this purpose.
Am Anger parking lot
- Type: Partial closure
- Duration: until 22.12.2023
- Reason: adjacent demolition work
- Details: A safety area must be set up.
2x Rautal
- Type: Complete closure
- Location: Junction with Naumburger Straße to Kaufland delivery entrance
- Duration: until 21.12.2023
- Reason: Surface course installation
- Details: A detour will be signposted on site.
- Type: Half-sided closure
- Location: from the junction with Erich-Kuithan-Straße to the junction with Ottoger-Mühlmann-Straße
- Duration: until 22.12.2023
- Reason: Asphalt work + construction of new sidewalk
- Details: The access road to Am Rosenhang remains closed. Residents must drive via the corridor path.
- Addition: Access to Erich-Kuithan-Straße is only permitted for bus traffic!
Remderoda
- Type: Complete closure
- Location: Road in the direction of Remderoda
- Duration: until 30.05.2024
- Reason: Laying of drinking water pipe
- Details: A detour via Münchenroda will be signposted.
Sandweg
- Type: Complete closure
- Place: House number 4-8
- Duration: until 22.12.2023
- Reason: Renewal of the district heating pipeline
- Details: The construction site can be passed safely on foot.
Schroeterstraße
- Type: Complete closure
- Location: from the junction with Strigelstraße to the junction with Am Friedensberg
- Duration: until 30.04.2024
- Reason: Fundamental expansion of the road
- Details: A second construction phase for the rest of the road is expected to follow from May 2024
Winzerlaer Straße
- Type: Sectional half-sided closures
- Location: in the area from Buchaer Straße to Mühlenstraße
- Duration: until 22.12.2023
- Reason: Connection changes to the Fichtlerwiesen / cable work
- Details: The construction work will be carried out in 8 construction phases at intervals of approx. 170m. Traffic will be guided alternately by means of mobile construction site traffic lights. The client is Satdtwerke Jena.
Wöllnitz
- Type: Temporary half-side closure + sidewalk closure
- Duration: until 15.12.2023
- Reason: Civil engineering work for laying fiber optic cables
- Details: The construction site can be passed safely on foot.
Ziegenhain
- Type: Temporary closures
- Duration: until 22.12.2023
- Reason: Continuation of civil engineering work for laying fiber optic cables
Zum Ziskauer Tal (Lützeroda)
- Type: Complete closure
- Duration: until 22.12.2023
- Reason: Civil engineering works (sewage; drinking water)
- Details: A detour will be signposted on site.
ANNOUNCEMENTS
Schweizerhöhenweg
- Reason: Construction work on elevated tank
- Details : The stopping restrictions and detour signs associated with the above-mentioned construction work will be deactivated. The construction work is going into its winter break and will not be continued until next year.