The construction site report for week 18 (01.- 07.05.2023)
Here is the current roadworks report for the 18th calendar week (01. - 07.05.2023).
Unless otherwise stated, you can walk or cycle past the roadworks.
COMPLETED CONSTRUCTION SITES
Carl-Zeiss-Promenade
- Electrical connections for a billboard have been laid.
Schrödingerstrasse
- The height of the manhole covers has been adjusted.
Spitzweidenweg
- Civil engineering work has been completed.
NEW CONSTRUCTION SITES / ROAD CLOSURES
Keßlerstraße
- Type: Half-sided closure
- Location: At house numbers 11 and 15
- Duration: 02.05.2023 to 10.05.2023
- Reason: Civil engineering works
- Details: Pedestrians will be guided safely to the opposite side of the footpath by means of barriers.
Sidewalk closure from Lutherplatz/ corner Saalbahnhofstraße to Dornburger Str. 52
- Duration: 02.05.2023 to 14.07.2023
- Reason: Installation/conversion of catenary masts
- Details: For the most part, pedestrians can pass the construction site safely. If there is a complete closure of the pavement, pedestrians and cyclists will be diverted accordingly. The construction work will begin on 02.05.2023 at Lutherplatz / corner of Saalbahnhofstraße and end on 14.07.2023 at Dornburger Straße 52.
EXISTING CONSTRUCTION SITES
Buchenweg
- Type: Half-sided closure
- Location: House number 34
- Duration: until 30.07.2023
- Reason: Construction site installation for the conversion of the adjacent school
- Details: Waiting is compulsory for vehicles meeting in the carriageway area.
Carl-Zeiss-Promenade
- Type: Half-sided closure
- Location: At bridge level
- Duration: until 19.05.2023
- Reason: Civil engineering works
- Details: Pedestrians and cyclists can pass the construction site safely.
Drackendorf
- Type: Temporary restrictions
- Duration: until 28.04.2022
- Reason: Civil engineering work for laying fiber optic cable
Dammstraße
- Location: Magnus-Poser-Straße to Schenkstraße (1st construction phase)
- Type: Complete closure
- Duration: until 30.05.2024
- Reason: Line and traffic system renewal
- Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.
1st construction phase: Magnus-Poser-Straße to Schenkstraße
2nd construction phase: Schenkstraße to Charlottenstraße
Erlanger Allee - cycle path connection between Lobeda-Ost and Lobeda-West
- Type: Closure of sections and path connections
- Location: between Theobald-Renner-Str. and Kastanienstraße junction and in the opposite direction
- Duration: until 29.02.2024
- Reason: Construction of a cycle path connection
- Details: In the first construction phase, the carriageway will be closed on one side and the pedestrian crossing at Platanenstraße to Paul-Schneider-Straße will be fully closed.
Erlanger Allee (bus stop Uni-Klinikum out of town)
- Type: Half-sided closure
- Duration: until 16.06.2023
- Reason: Renewal of the bus stop
- Details: The replacement bus stop will be located in the immediate vicinity. Congestion is to be expected as there is a lane narrowing. Pedestrians and cyclists can pass the construction site safely.
Fiber optic cable expansion in Laasan
- Type: Temporary restrictions
- Duration: until 16.06.2023
- Reason: Renewal of the bus stop
- Details: Due to the laying of the fiber optic cable commissioned by Deutsche Telekom, half-sided road closures and local full closures must be expected.
Johannisstraße
- Type: Restrictions
- Location: Junction with Jenergasse to Johannisstaße 17
- Duration: until 05.05.2023
- Reason: Media relocation
- Details: Pedestrians can pass the construction site safely. Cyclists must dismount during the construction period.
Julius-Schaxel-Straße
- Type: Complete closure
- Location: Entrance to local traffic to Göschwitzer Straße junction (Fiebig car dealership)
- Duration: until 31.08.2023
- Reason: Road expansion incl. pipe laying
- Details: The construction site can be passed on foot.
Lessingstraße
- Type: Complete closure
- Duration: until 26.05.2023
- Reason: Civil engineering works
- Details: During the construction period, Lessingstraße is not accessible from the direction of Am Steiger. Fröbelstieg can only be accessed from the direction of Philosophenweg.
Lindenhöhe
- Type: Complete closure
- Duration: until 05.05.2023
- Reason: Civil engineering works
- Details: The construction site can be safely passed on foot.
2x Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld to just before the Lichtenhainer Brücke bridge
- Duration: until 30.07.2023
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
- Type: Closure of partial areas
- Location: From the main stadium access road to Roland-Ducke-Weg
- Duration: until 04.08.2023
- Reason: Expansion of the road and ancillary facilities
- Details: Access to the Oberaue will always be possible. In the first construction phase, work is currently underway from the main stadium access road to just before the Roland-Ducke-Weg junction. The construction site can be passed, but obstructions are to be expected. Cyclists can bypass the construction site safely and quickly. A detour has been set up and signposted for this purpose.
- In the 2nd construction phase from 24.04.2023, the main access road to the stadium will be closed on one side. Traffic will be guided alternately by a mobile traffic light system.
Thomas-Münzer-Weg
- Type: Complete closure
- Location House number 4
- Duration: until 30.06.2023
- Reason: Construction of a residential building
- Details: The full closure is indicated by means of planning boards from both Jägerbergstraße and Max-Gräfe-Gasse. The restricted area must be driven around extensively. The construction site can be safely passed on foot and by bike.
Unterm Sande (Maua)
- Type: Half-sided closure
- Duration: until 19.05.2023
- Reason: Cable laying
Ziegenhainer Straße
- Type: Full closure
- Place: House number 99
- Duration: until 12.05.2023
- Reason: Media relocation
- Details: A detour will be signposted on site. Pedestrians and cyclists can pass the bus stop safely.
Access to Gemdental
- Type: Complete closure
- Location: Access to Gemdental road (Gemdental / Am Jenzig / Am Erlkönig junction)
- Duration: until 09.06.2023
- Reason: Development of the local heating network for the "Erlenhöfe" residential area
- Details: Residents can reach Gemdental street via Karl-Liebknecht-Straße and an additional path to Am Jenzig street will be upgraded. A detour for the church cycle path will be signposted. Please refer to the appendix for information on access to the Talstein nursery.
Zufahrtsregelung Gärtnerei Talstein
© Kommunalservice Jena
To the Ziskauer valley (Lützeroda)
- Type: Complete closure
- Duration: until 27.10.2023
- Reason : Civil engineering works (sewage; drinking water)
- Details: A detour will be signposted on site.
ANNOUNCEMENT
Ernst-Haeckel-Straße
- Type: Complete closure
- Duration: 08.05.2023 to 15.07.2023
- Reason: Renewal of the sewer
- Details: Traffic will be diverted via Knebelstraße/ Am Eisenbahndamm or via Magdelstieg/ Tatzendpromenade.