The current construction site report for Jena
Here is the current construction site report for the 11th calendar week of 2022.
Unless otherwise indicated, cyclists and passers-by will pass the roadworks.
Finished roadworks
Road closures in Jena-North
- In Rautal, at the level of the drinking water tank - no more full closure.
- Footpaths in Closewitzer Straße fully accessible again.
- Half-sided closure in Ottogerd-Mühlmann-Straße completed.
New construction sites / closures
Brändströmstraße and Gabelsbergerstraße
- Type: Complete closure
- Location: Gabelsbergerstraße and Brändströmstraße intersection area
- Duration: until 17.06.2022
- Reason: Renewal of the sewage pipes
Eichplatz
- Type: Partial closure
- Duration: on Monday, 07.03.2022, 17.00 - 22.00 hrs
- Reason: rally
Kollegiengasse
- Type: New installation of the full closure
- Location: between Nonnenplan and Löbderstraße
- Duration: until 30.04.2022
- Reason: Civil engineering works
- Details: A detour is signposted.
Existing construction sites
"Bridge in front of the Neutor"
- Type: Complete closure
- Duration: until 30.04.2022
- Reason: New construction of the bridge
- Traffic will be diverted as follows:
- out of town via Erbertstraße - Ernst-Haeckel-Straße
- into the city via Ernst-Haeckel-Straße - Schillerstraße - Teichgraben
- Details: Underpass to Paradies fully closed - detour signposted
Buchenweg
- Type: Half-sided closure
- Location: House number 34
- Duration: until 12.07.2022
- Reason: Construction site installation for the conversion of the adjacent school
- Details: Waiting is compulsory for vehicles meeting in the carriageway area.
Dornburger Straße
- Type: Complete closure
- Location: from the junction with Friedrich-Wolf-Straße to the junction with An der Eule
- Duration: until 30.06.2022
- Reason: Civil engineering works
- Details: A detour will be signposted. Pedestrians can pass the construction site safely.
Emil-Wölk-Straße (bus stop)
- Type: Closure on one side
- Location: Karl-Marx-Allee at Emil-Wölk-Straße (towards the traffic circle)
- Duration: until 31.03.2022
- Reason: New construction of bus stop
- Details: Traffic will be diverted via Stauffenbergstraße.
Hornstraße
- Type: Complete closure
- Duration: until 31.03.2022
- Reason: Renovation of the "Dornröschen" daycare center
- Details: Pedestrians can pass.
Karl-Liebknecht-Straße
- Type: Complete closure
- Location: House number 34 - 44
- Duration: until 01.04.2022
- Reason: Civil engineering works
- Details: Pedestrians will be diverted to the opposite sidewalk.
Kollegiengasse
- Type: Complete closure
- Location: between Nonnenplan and Löbderstraße
- Duration: until 30.04.2022
- Reason: Civil engineering works
- Details: A detour is signposted.
Oberaue
- Type: Complete closure
- Location: House number 20 to the Lichtenhainer bridge
- Duration: until 31.03.2022
- Reason: Work on the high-pressure gas pipeline
- Details: The running hall and adjacent sports fields can be accessed. Access in the direction of Lichtenhainer Brücke is not possible. A corresponding detour for pedestrians and cyclists is signposted.
Schützenhofstraße
- Type: Half-sided closure
- Location House number 74-78
- Duration: until 01.07.2022
- Reason: Construction site installation for the conversion of the adjacent apartment block
- Details: Pedestrians can pass safely.
Announcements
Blochmannstraße
- Type: Complete closure
- Duration: 21.03. - 17.06.2022
- Reason: Renewal of the supply lines