Jena construction site report for the 14th calendar week (01. - 07.04.2024)
Unless otherwise indicated, you can get past the roadworks on foot and by bike.
New closures / obstructions
Neugasse
- Type: Complete closure
- Duration: 02 - 04.04.2024
- Reason: Paving work
Kahlaische Straße at house numbers 50 and 54
- Type: temporary half-sided closure
- Duration: 02. - 05.04.2024
- Reason: Search shafts for the purpose of a cable route
- Details: Traffic is regulated by means of mobile traffic lights
- Reason: Paving work
Completed closures
Full closure of Frommannstraße
Road surface renovation completed.
Half-sided closure of Naumburger Straße at house number 161
Work on the supply lines completed.
Partial closure of Bundesstraße 7
Road surface renovation completed.
Existing closures
Brückenstraße / Leibnizstraße
- Type: Half-sided closure in the form of a one-way street regulation
- Duration: until 10.05.2024
- Reason: Laying of district heating pipe
- Details: The one-way street is passable in the direction of Kunitz. Out-of-town traffic will be diverted via the street "Am Steinbach".
- Note: In the period from 03. to 18.04.2024, the one-way street regulation will be temporarily suspended, so that Brückenstraße can be used on both sides during this period. This is due to important work being carried out by Jenaer Nahverkehr on the tracks in Naumburger Straße between Rautal and Flurweg. In order to maintain the flow of traffic, the existing traffic organization will be temporarily suspended. Once the work in Naumburger Straße has been completed, the one-way traffic organization in Brückenstraße will be reactivated.
Dammstraße
- Type: Full closure
- Duration: until 30.05.2024
- Reason: Laying of pipes and renewal of the road surface
- Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.
1st construction phase: Magnus-Poser-Straße to Schenkstraße
2nd construction phase: Schenkstraße to Charlottenstraße
Erlanger Allee - cycle path connection
- Type: Temporary closure
- Location: between Lobeda-Ost and Lobeda-West
- Duration: until 03.05.2024
- Reason: Remaining work
Erlanger Allee
- Type: Traffic restrictions
- Location: from the pedestrian crossing at Paul-Schneider-Straße
- Duration: until 19.04.2024
- Reason: Road surface renovation
- Details: There will be various construction phases during the construction period. Detour signs will be set up on site. The construction site can be passed safely on foot. Please refer to the diagrams for further information.
Detour plan Erlanger Allee
Streicher traffic engineering
Erlanger Allee construction phase 1
Streicher traffic engineering
Erlanger Allee construction phase 2
Streicher traffic engineering
Erlanger Allee construction phase 3
Streicher traffic engineering
Ernst-Pfeiffer-Straße
- Type: Complete closure
- Duration: until 05.04.2024
- Reason: Surface course + boarding installation
- Details: The construction site can be passed safely on foot
Fritz-Reuter-Straße
- Type: Full road closure in sections
- Duration: until 12.04.2024
- Reason: Reconstruction of the combined sewer
Grenzstraße
- Type: Half-sided closure
- Location: At house number 2 - 4
- Duration: until 29.03.2024
- Reason: Construction of an apartment building
- Details: Pedestrians will be guided safely past the construction site using an emergency pedestrian route.
Hermann-Löns-Straße
- Type: Closure on one side
- Location: at the level of the crosswalk to the junction with Mühlenstraße
- Duration: until 31.07.2024
- Reason: Laying of medium voltage cable
- Details: Traffic will be guided past the construction site by means of a mobile traffic light system
Johannisstraße
- Type: Traffic restrictions
- Location: Eastern Johannisstraße 17 - 22
- Duration: until 26.04.2024
- Reason: Remaining work laying district heating (Stadtwerke Jena)
- Details: The construction site can be passed safely on foot. Cyclists must push due to insufficient remaining width. Provided the weather cooperates, the construction work can be completed ahead of schedule at the end of March. This means that there should be as little disruption as possible for outdoor catering and visitors to the spring market.
Lichtenhainer Oberweg
- Type: Various restrictions
- Location: Tatzendpromenade junction to the access road to the P10 Zeiss parking lot
- Duration: 25.03. - 31.12.2024
- Reason: Laying of district heating pipeline
- Details: From 25.03. to 30.06.2024, the work will initially be carried out with the road closed on one side. For this purpose, Lichtenhainer Oberweg will become a one-way street in the direction of Lichtenhain. A detour via Mühlenstraße will be signposted for traffic heading into the city. From July, the Lichtenhainer Oberweg will have to be closed to traffic in sections. The construction site will gradually work its way from the upper part of Lichtenhainer Oberweg towards Tatzendpromenade. Detour will be signposted via Friedrich-Körnerstrasse, Döbereinerstrasse and Philipp-Müller-Strasse. Stadtwerke Energie Jena-Pößneck asks for your understanding for the restrictions.
Lobeda Ost and Lobeda Altstadt
- Type: Temporary half-side closure + sidewalk closure
- Duration: until 07.06.2024
- Reason: Civil engineering work for laying fiber optic cables
- Details: The construction site can be passed safely on foot.
Löbichauer Straße
- Type: Complete closure
- Location: lower Löbichauer Straße (Karl-Liebknecht-Straße to Eschenplatz)
- Duration: until 30.11.2024
- Reason: Civil engineering works
- Details: Pedestrians will be safely rerouted.
2x Naumburger Straße
- Type: Half-sided closure
- Duration: until 30.04.2024
- Reason: Reconstruction of the streetcar stop "Stifterstraße" + installation of track replacement
- Details: During the construction period, a one-way street will be installed from the Zitzmannstraße junction to Altenburger Straße. The one-way street is passable in the direction of the city center. The construction site can be passed safely on foot.
- Addition: In the period 25.03. - 05.04.2024, additional civil engineering work must be carried out at the local traffic construction site. This will involve removing large quantities of earth from the construction site. In order to be able to carry out this work using excavators, the road must be fully closed in order to maintain the safety distances. The work should be completed by the end of the Easter vacations. Afterwards, the road will be closed again on one side.
- Type: Half road closure
- Location: At house number 161
- Duration: until 05.04.2024
- Reason: Work on the supply lines
- Details: The construction site can be passed safely on foot.
Nollendorfer road
- Type: Complete closure
- Location: between Thomas-Mann-Straße and Dornburger Straße
- Duration: until 30.05.2024
- Reason: Major road renovation
2x Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
- Duration: until 30.04.2024
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
- Type: Access restrictions
- Duration: until 17.05.2024
- Reason: Remaining work
- Details: The mobile traffic light system will be reactivated. Entry to the Oberaue is possible.
Remderoda
- Type: Complete closure
- Location: Road in the direction of Remderoda
- Duration: until 30.05.2024
- Reason: Laying of drinking water pipe
- Details: A detour via Münchenroda will be signposted.
Schroeterstraße
- Type: Complete closure
- Location: from the junction with Strigelstraße to the junction with Am Friedensberg
- Duration: until 30.04.2024
- Reason: Fundamental expansion of the road
- Details: A second construction phase for the rest of the road is expected to follow from May 2024
Winzerlaer Straße
- Type: Half-sided closure
- Location: between the junction of Adolf-Reichwein-Straße and the junction of Rosalind-Franklin-Straße
- Duration: until 05.04.2024
- Reason: Reconstruction work
- Details: During the construction period, an emergency sidewalk and a construction site access/exit will be set up. Motorized individual traffic will be guided past the construction site by means of a mobile traffic light system.
Wöllnitz
- Type: Temporary road closure on one side + footpath closure
- Duration: until 31.05.2024
- Reason: Civil engineering work for laying fiber optic cables
- Details: The construction site can be passed safely on foot.
Ziegenhain
- Type: Traffic restrictions
- Duration: until 30.03.2024
- Reason: Fiber optic expansion
Announcements
Teichgraben
- Type: Half-sided closure
- Duration: 08.04. - 24.05.2024
- Reason: Renovation of the bus stop (accessibility) incl. surface course work
- Details: Traffic will be maintained by means of one-way traffic regulations. The construction site can be safely passed on foot in the longitudinal direction. House entrances and stores are within walking distance. Replacement stops will be set up by local transport, further information can be found at www.stadtwerke-jena.de/nahverkehr
- Addition: Please do not park any vehicles in the Holzmarkt area. It must be possible for local transport to pass through this area safely and smoothly. The public order office will carry out increased checks in the Holzmarkt area.
Hermann-Löns-Straße
- Type: Temporary half-sided closure
- Location: At Mühlenstraße level
- Duration: 08 - 12.04.2024
- Reason: Search shafts for the purpose of a cable route
- Details: Traffic will be diverted past the construction site by means of signage.
- Note: In addition, a one-way street will be set up in Mühlenstraße between the junction with Hermann-Löns-Straße and the junction with Am Knollen, which can be driven on in the direction of Kahlaische Straße.
Ernst-Haeckel-Straße
- Type: Complete closure
- Location: between Erbertstraße and Sellierstraße
- Duration: 15.04. - 30.06.2024
- Reason: Work on the drinking water pipeline
- Details: Traffic will be diverted via the following route: Vor dem Neutor - Knebelstraße - Am Eisenbahndamm - Fürstengraben
Rautal
- Type: Complete closure
- Location: between Erich-Kuithan-Straße and Naumburger Straße
- Duration: 08.04. - 26.04.2024
- Reason: Road surface renovation (postponed to 2024 due to weather conditions)
- Details: Traffic coming from Closewitz will be informed of the full closure or diverted at Closewitzer Straße, other traffic coming from Jägerbergstraße/Am Heiligenberg should use the detour via Erich-Kuithan-Straße.
2x Löbstedter Straße
- Type: Half-sided closure
- Location: House numbers 9 - 11
- Duration: 08.04. - 19.04.2024
- Reason: Civil engineering work for a media connection
- Type: Complete closure
- Location: House number 49 a
- Duration: 08.04. - 19.04.2024
- Reason: Construction of a domestic drinking water connection
- Details: Traffic will be diverted via Schlachthofstraße.
Scharnhorststraße
- Type: Complete closure
- Location: between Leipziger Straße and Camburger Straße
- Duration: 09.04.
- Reason: Civil engineering work for renovation work on the gas pipeline
Karl-Liebknecht-Straße at the level of Erlenhöfe
- Type: Half-sided closure
- Duration: 08.04. - 03.05.2024
- Reason: Construction of a new sidewalk
- Details: Traffic will be guided by construction site traffic lights. Longer waiting times and obstructions are to be expected.
Schützenhofstraße
- Type: Complete closure
- Location: At the level of house numbers 36 to 38
- Duration: 08.04. - 19.04.2024
- Reason: Construction of a domestic drinking water connection
- Details: During this time, bus traffic will be routed via Schützenhofstraße to the north, which is why large areas will have to be closed to traffic. Information boards and a detour will be signposted.
Naumburger Straße
- Type: Closure on one side
- Location: between Rautal and Flurweg
- Duration: 16.04. - 18.04.2024
- Reason: Surface opening for local traffic
- Details: Traffic will be guided past the construction site on both sides by means of traffic lights.
- Note: During this period, Brückenstraße is passable in both directions.