Jena construction site report for the 18th calendar week (29.04. - 05.05.2024)

26.04.2024

Unless otherwise indicated, you can get past the roadworks on foot and by bike.

New closures / obstructions

Ottogerd-Mühlmann-Straße

  • Type: Complete closure
  • Location: Corner of Rautal
  • Duration: 29.04. - 03.05.2024
  • Reason: Remaining work
  • Details: The roadworks can be safely passed on foot. Road users who want to reach Gotthard-Neumann-Straße can do so via the following route: Rautal - Erich-Kuithan-Straße - Zitzmannstraße - Schützenhofstraße and Ottogerd-Mühlmann-Straße.

Finished closures

Erlanger Allee to Kastanienstraße

  • NOTE: Unfortunately, it has not yet been possible to apply road markings due to the weather. For this reason, the newly extended area will be signposted with a speed limit of 30 km/h. We ask all road users to drive with caution and consideration on the newly extended road section.

Göschwitzer Straße

  • Repair work on the bridge has been completed.

Johannisstrasse

  • District heating installation is complete.

Rautal

  • Road surface renovation is complete.

Existing road closures

Angergasse

  • Type: Complete closure
  • Duration: until 10.05.2024
  • Reason: Civil engineering works
  • Details: People on foot can walk around the construction site via Quergasse.

Brückenstraße

  • Type: Half-sided closure in the form of a one-way street regulation
  • Location: between Leibnizstraße and Naumburger Straße
  • Duration: until 24.05.2024
  • Reason: Laying of district heating pipeline
  • Details: The one-way street is passable in the direction of Kunitz. Out-of-town traffic will be diverted via the street "Am Steinbach".

Dammstraße

  • Type: Complete closure
  • Duration: until 30.05.2024
  • Reason: Laying of pipes and renewal of the road surface
  • Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.
  1. Construction phase: Magnus-Poser-Straße to Schenkstraße
  2. Construction phase: Schenkstraße to Charlottenstraße

Erlanger Allee - cycle path connection

  • Type: Temporary closure
  • Location: between Lobeda-Ost and Lobeda-West
  • Duration: until 03.05.2024
  • Reason: Remaining work

Border road

  • Type: Half-sided closure
  • Location: At house numbers 2 - 4
  • Duration: until 31.05.2024
  • Reason: Construction of an apartment building
  • Details: Pedestrians will be guided safely past the construction site using an emergency pedestrian route.

Hermann-Löns-Straße

  • Type: Closure on one side
  • Location: up to the junction with Mühlenstraße
  • Duration: until 31.07.2024
  • Reason: Laying of a medium-voltage cable
  • Details: Traffic will be guided past the construction site by means of a mobile traffic light system

2x Karl-Liebknecht-Straße

  • Type: Half-sided closure
  • Location: At the level of Erlenhöfe
  • Duration: until 03.05.2024
  • Reason: New sidewalk construction
  • Details: Traffic will be guided by construction site traffic lights. Longer waiting times and obstructions are to be expected.
  • Type: selective restrictions in sections
  • Location: from the junction with Rosenstraße to the junction with Karl-Günther-Straße
  • Duration: until 31.05.2024
  • Reason: Maintenance work on the tracks
  • Details: The construction areas (moving construction site) are short and can be avoided with mutual consideration.

Keßlerstraße

  • Type: Complete closure
  • Location: between Göschwitzer Straße and Geraer Straße (1st construction phase)
  • Duration: until 04.06.2024
  • Reason: fundamental expansion in the area of Grenzstraße
  • Details: A detour will be signposted. Pedestrians can pass the construction site safely.

Lichtenhainer Oberweg

  • Type: Various restrictions
  • Location: Tatzendpromenade junction to the access road to the P10 Zeiss parking lot
  • Duration: until 31.12.2024
  • Reason: Laying of district heating pipeline
  • Details: From 25.03. to 30.06.2024, the work will initially be carried out with the road closed on one side. For this purpose, Lichtenhainer Oberweg will become a one-way street in the direction of Lichtenhain. A detour via Mühlenstraße will be signposted for traffic heading into the city. From July onwards, the Lichtenhainer Oberweg will have to be fully closed in sections. The construction site will gradually work its way from the upper part of Lichtenhainer Oberweg towards Tatzendpromenade. Detour will be signposted via Friedrich-Körnerstrasse, Döbereinerstrasse and Philipp-Müller-Strasse. Stadtwerke Energie Jena-Pößneck asks for your understanding for the restrictions.

Lobeda Ost and Lobeda Altstadt

  • Type: Temporary half-side closure + sidewalk closure
  • Duration: until 07.06.2024
  • Reason: Civil engineering work for laying fiber optic cables
  • Details: The construction site can be passed safely on foot.

Lutherstrasse

  • Type: Half-sided closure + sidewalk closure
  • Location: in westbound direction (Weimar) from the Carl-Zeiß-Platz junction
  • Duration: until 03.05.2024
  • Reason: Replacement of the Telekom cable duct in the sidewalk
  • Details: The detour leads via Carl-Zeiß-Platz / Blumenstraße. The one-way street in Blumenstraße will be turned around, a replacement stop of the Jena public transport will be arranged in Blumenstraße for the closed stop in Lutherstraße.

Eastern Löbdergraben

  • Type: Complete closure
  • Location: between Steinweg and Lutherplatz
  • Duration: until 09.08.2024
  • Reason: Roadworks and media relocation
  • Details: Traffic will be diverted via the following route Am Eisenbahndamm - Am Anger - Lutherplatz.
    People on foot use the western side of Löbdergraben.

Löbichauer Straße

  • Type: Complete closure
  • Location: Lower Löbichauer Straße (Karl-Liebknecht-Straße to Eschenplatz)
  • Duration: until 30.11.2024
  • Reason: Civil engineering works
  • Details: Pedestrians will be safely rerouted.

Naumburger Straße

  • Type: Half-sided closure
  • Duration: until 30.07.2024
  • Reason: Reconstruction of the streetcar stop "Stifterstraße" + installation of track replacement
  • Details: During the construction period, a one-way street will be installed from the Zitzmannstraße junction to Altenburger Straße. The one-way street is passable in the direction of the city center. The construction site can be passed safely on foot.
  • Addition: In the period 25.03. - 31.07.2024, additional civil engineering work must be carried out at the local transport construction site. Due to the additional track drainage with associated shafts, the road must remain fully closed in order to work in the construction area with appropriate equipment from the roadway. Individual traffic will not be able to flow due to the safety regulations to be observed, after which the half-sided closure will come into force again. As a result, the buses of the rail replacement service (SEV line E) will continue to take an alternative route. The Stifterstraße stop is still closed and the Altenburger Straße replacement stop cannot be reached. Passengers are requested to use the Merseburger Straße stop instead.

Nollendorfer Straße

  • Type: Complete closure
  • Location: between Thomas-Mann-Straße and Dornburger Straße
  • Duration: until 30.05.2024
  • Reason: Fundamental road renovation

2x Oberaue

  • Type: Complete closure
  • Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
  • Duration: until 30.04.2024
  • Reason: Work on the stadium grandstand
  • Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
  • Type: Access restrictions
  • Duration: until 17.05.2024
  • Reason: Remaining work
  • Details: The mobile traffic light system will be reactivated. Entry to the Oberaue is possible.

Remderoda

  • Type: Complete closure
  • Location: Road in the direction of Remderoda
  • Duration: until 30.05.2024
  • Reason: Laying of drinking water pipe
  • Details: A detour via Münchenroda will be signposted.

Schroeterstraße

  • Type: Complete closure
  • Location: from the junction with Strigelstraße to the junction with Am Friedensberg
  • Duration: until 30.04.2024
  • Reason: Fundamental expansion of the road
  • Details: A second construction phase for the rest of the road is expected to follow from May 2024

Pond ditch

  • Type: Half-sided closure
  • Duration: until 24.05.2024
  • Reason: Renovation of the bus stop (accessibility) incl. surface course work
  • Details: Traffic will be maintained by means of one-way traffic regulations. The one-way street can be driven on in the direction of Leutragraben. A one-way street will also be set up in the Nonnenplan area.
  • The cab ranks from Nonnenplan that are no longer required will be relocated. The replacement location will be set up in Kollegiengasse opposite the C&A clothing store (up to the Nonnenplan junction).
  • A replacement stop will be set up by local transport in Nonnenplan, further information can be found at www.stadtwerke-jena.de/nahverkehr.
  • Addition: Please do not park any vehicles in the Holzmarkt area. It must be possible for local transport to pass through this area safely and smoothly. The public order office will carry out increased checks in the Holzmarkt area.
  • Attention: From 14.05. to 16.05.2024, the above-mentioned area will be completely closed. During the closure period, the surface course will be installed in the bus stop area. Road users who want to drive in the direction of Leutragraben must bypass the full closure via Holzmarkt and Grietgasse.

Wöllnitz

  • Type: Temporary half-side closure + sidewalk closure
  • Duration: until 31.05.2024
  • Reason: Civil engineering work for laying fiber optic cables
  • Details: The construction site can be passed safely on foot.

Ziegenhain

  • Type: Traffic restrictions
  • Duration: until 30.04.2024
  • Reason: Fiber optic expansion

Announcements

Karl-Liebknecht-Straße

  • Type: Complete closure
  • Location: between Feldstraße and Brändströmstraße
  • Duration: 06.05. - 02.08.2024
  • Reason: Laying of combined sewer on behalf of Stadtwerke Jena
  • Details: Traffic will be widely diverted via Wiesenstraße / Am Anger / Camsdorfer Brücke. Cycle traffic will be diverted via: Pestalozzistraße - Gabelsbergerstraße - Am Steinborn. Streetcar traffic will continue to run despite the construction work.

Ernst-Haeckel-Straße

  • Type: Complete closure
  • Location: between Erbertstraße and Sellierstraße
  • Duration: 06.05. - 30.06.2024
  • Reason: Work on the drinking water pipeline
  • Details: Traffic will be diverted via the following route: Vor dem Neutor - Knebelstraße - Am Eisenbahndamm - Fürstengraben. The construction site can be passed safely on foot.