Jena construction site report for the 29th calendar week (15 - 21.07.2024)
Unless otherwise indicated, you can get past the roadworks on foot and by bike.
New closures / obstructions
Kahlaische Strasse
-
Type: Complete closure
-
Location: At the junction with Sandweg
-
Duration: 15.07. - 19.07.2024, daily from 8:30 pm - 5:00 am
-
Reason: Connection work
-
Details:Residents can reach Kahlaische Straße via Mühlenstraße. A detour will be signposted. The closurecan bepassedon foot and by bike.
Completed closures
Buchaer Straße
-
Type: Complete closure
-
Location: between house number 6 and Ammerbacher Straße
Otto-Schott-Straße
-
Type: Half-sided closure
-
Location: At house number 7
Existing closures
Brückenstraße
-
Type: Closure on one side
-
Duration: until 17.07.2024
-
Reason: Laying of medium-voltage cables, low-voltage cables and fiber optic cables
-
Details: To begin with, the sidewalk in Brückenstraße will be fully closed in the area of the widened intersection. In addition, the road in the area of the parking lane will be required as a construction site facility. The construction site can be passed on foot. Traffic can travel in both directions. However, a one-way street will have to be set up again as the work progresses. This will be announced well in advance.
-
Addition: Brückenstr. between Leibnizstraße and Naumburger Straße
Partial closure until 19.07.2024 with one-way street regulation (direction of travel Kunitz)
Reason: Completion of cable laying
Dammstraße
-
Type: Full closure
-
Duration: until 31.12.2024
-
Reason: Cable laying and renewal of the road surface
-
Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.
2nd construction phase: Schenkstraße to Charlottenstraße
2x Dornburger Straße
-
Type: Various road closures
-
Location House number 6
-
Start: 19.06.2024
-
Reason: Construction of a new house
-
Details: From this date, the sidewalk along the property and the adjacent parking lane will be required and closed for the construction site equipment. From 15.08.2024, the roadway out of town will also be required until the shell of the building is completed. Out-of-town traffic will be diverted via Spitzweidenweg and Nollendorfer Straße.
-
Type: Spot closure on one side only
-
Location: from the Altenburger Straße stop to the Nordschule school
-
Duration: until 09.08.2024
-
Reason: The renewal of the overhead contact line system of the Jena public transport system makes it necessary to close one side of the road at certain points and to close the pavement at the various mast locations during daily working hours.
Erbertstraße
-
Type: Complete closure
-
Location: as well as the southern part of the Ernst-Haeckel-Straße parking lot
-
Duration: until 30.06.2024
-
Reason: Work on the drinking water pipeline
Ernst-Abbe-Platz
-
Duration: until 30.08.2024
-
Reason: Extensive construction work in the track area
-
Details: Crossing options for pedestrians will be set up.
Grenzstraße
-
Type: Closure on one side
-
Location: At house numbers 2 - 4
-
Duration: until 19.07.2024
-
Reason: Construction of an apartment building
-
Details: An emergency footpath leads past the construction site.
Großschwabhäuser Street
-
Type: Complete closure
-
Location: At house number 1
-
Duration: until 19.07.2024
-
Reason: Work on the supply line
-
Details: Traffic will be routed via the main road / B7 junction. Traffic will be regulated by traffic lights. Traffic jams are to be expected.
Kahlaische Straße
-
Type: Complete closure
-
Location: House numbers 68 and from the junction with Beutenbergstraße to house number 46
-
Duration: until 31.07.2024 (end of the summer vacations)
-
Reason: Media relocation in the sidewalk area by Stadtwerke Jena
-
Details: The road must serve as an emergency footpath and as a construction site facility for the work to be carried out. The outbound lane is part of the construction site. The lane towards the city center serves as an alternative route and is also open to bicycle traffic. Residents - especially businesses - will be guaranteed access to their properties. The large-scale detour will be via Stadtrodaer Straße. Jenaer Nahverkehr will provide information on timetable changes on this route.
Karl-Liebknecht-Straße
-
Type: Complete closure
-
Location: between Feldstraße and Brändströmstraße
-
Duration: until 02.08.2024
-
Reason: Laying of combined sewer on behalf of Stadtwerke Jena
-
Details: Traffic will be widely diverted via Wiesenstraße - Am Anger - Camsdorfer Brücke. Cycle traffic will be diverted via Pestalozzistraße - Gabelsbergerstraße - Am Steinborn. Streetcar traffic will continue to run despite the construction work.
Keßlerstraße
-
Type: Complete closure
-
Location: between Göschwitzer Straße and Geraer Straße (1st construction phase)
-
Duration: until 31.07.2024
-
Reason: fundamental expansion in the Grenzstraße area
-
Details: A detour will be signposted. The construction site can be passed on foot.
-
Addition: From 15-07 - 30.11.2024 a full closure between the Geraer Staße junction up to the railroad bridge is necessary for the work.
Church square
-
Type: Traffic restrictions
-
Location: Around the town church
-
Duration: until 30.12.2024
-
Reason: extensive construction work
-
Details: The construction site can be passed on foot, access to the town church is guaranteed during the entire construction period. Saalstraße will be fully closed to transit/delivery traffic.
Lichtenhainer Oberweg
-
Type: Various restrictions
-
Location: Tatzendpromenade junction to access to the P10 Zeiss parking lot
-
Duration: until 31.12.2024
-
Reason: Laying of district heating pipeline
-
Details: From July, the Lichtenhainer Oberweg will have to be fully closed in sections. The construction site is gradually working its way from the upper part of Lichtenhainer Oberweg towards Tatzendpromenade. Detour will be signposted via Friedrich-Körnerstrasse, Döbereinerstrasse and Philipp-Müller-Strasse. Stadtwerke Energie Jena-Pößneck asks for your understanding for the restrictions.
Lobeda Ost and Lobeda Altstadt
-
Type: Temporary half-side closure + sidewalk closure
-
Duration: until 26.07.2024
-
Reason: Civil engineering work for laying fiber optic cables
-
Details: The construction site can be passed safely on foot
Mädertal
-
Type: Complete closure
-
Location: At house number 1
-
Duration: until 19.07.2024, daily from 07:00 - 16:00
-
Reason: Laying of supply lines
-
Details: The closure canbesafelypassed on foot and by bike.
Eastern Löbdergraben
-
Type: Complete closure
-
Location: between Steinweg and Lutherplatz
-
Duration: until 09.08.2024
-
Reason: Roadworks and media relocation
-
Details: Traffic will be diverted via the following route Am Eisenbahndamm - Am Anger - Lutherplatz.
The construction site can be crossed on foot via the footpath on the western side of Löbdergraben. -
Addition: A new traffic route has been set up for road users who want to drive from the eastern Löbdergraben towards the Fürstengraben junction. It is possible to follow the signs and drive through the bus stop area in the direction of the Fürstengraben junction. When entering the track area from Löbdergraben, the streetcar must be given priority. Please drive carefully and considerately in this area.
Löbdergraben
-
Type: Narrowing of lane
-
Start: until 09.08.2024
-
Reason: To ensure the construction work on the outdoor facilities of the Inselplatz campus
-
Details: The eastbound lanes on Lutherplatz (Am Anger) will be narrowed to one lane over a distance of approx. 50.00 m from Löbdergraben. In Fürstengraben, the traffic flows will be separated into right-turning and straight-ahead vehicles.
Löbichauer Straße
-
Type: Complete closure
-
Location: Lower Löbichauer Straße (Karl-Liebknecht-Straße to Eschenplatz)
-
Duration: until 30.11.2024
-
Reason: Civil engineering works
-
Details: The sidewalk will be rerouted.
Max-Gräfe-Gasse
-
Type: Complete closure
-
Location: At house number 17
-
Start: until 19.07.2024
-
Reason: Demolition work
-
Details: The construction site can be passed safely on foot.
Martin-Niemöller-Straße
-
Type: Half-sided closure
-
Start: until 31.08.2024
-
Reason: Relocation of medium voltage road
-
Details: The construction site can be passed safely on foot.
Moritz-von-Rohr-Straße
-
Type: Closure on one side
-
Location: at the level of the university of applied sciences
-
Duration: until 31.07.2024
-
Reason: Civil engineering works (medium voltage cable)
Naumburger Straße
-
Type: Full closure Closure
-
Duration: until 31.07.2024
-
Reason: Conversion of the "Stifterstraße" streetcar stop and fundamental expansion of the track system
-
Addition: In the period 25.03. - 31.07.2024, additional civil engineering work must be carried out at the local transport construction site. Due to the additional track drainage with associated shafts, the road must remain fully closed in order to work on the construction site from the roadway with the appropriate equipment. Individual traffic cannot flow due to the safety regulations to be observed.
-
As a result, the buses of the rail replacement service (SEV line E) will continue to take an alternative route.
The Stifterstraße stop is still unavailable and the Altenburger Straße replacement stop cannot be reached. Passengers are requested to use the Merseburger Straße stop instead.
Nollendorfer Straße
-
Type: Complete closure
-
Location: between Thomas-Mann-Straße and Dornburger Straße
-
Duration: until 30.09.2024
-
Reason: fundamental road renovation
Oberaue
-
Type: Complete closure
-
Location: From the Saaleeingang Ernst-Abbe-Sportfeld to just before the Lichtenhainer Brücke bridge
-
Duration: until 30.09.2024
-
Reason: Work on the stadium grandstand
-
Details: The Lichtenhain Bridge is not affected by the closure. A detour for cyclists and pedestrians is signposted.
Remderoda
-
Type: Complete closure
-
Location: Road in the direction of Remderoda
-
Duration: until 15.09.2024
-
Reason: Laying of drinking water pipe
-
Details: A detour via Münchenroda will be signposted.
Schillerstraße
-
Type: Speed reduced to 20 km/h
-
Duration: until 18.08.2024
-
Reason: To increase safety for all road users during the Kulturarena
-
Details: Barrier grids will also be installed to guide traffic safely.
Schroeterstrasse
-
Type: Complete closure
-
Location: from the junction with Strigelstraße to the junction with Am Friedensberg
-
Duration: until 30.10.2024
-
Reason: fundamental expansion of the road
Wöllnitz pedestrian bridge
-
Type: Complete closure
-
Duration: until 09.08.2024
-
Reason: Maintenance work incl. renewal of the surface
-
Details: Cyclists and pedestrians must use the traffic lights at Wöllnitz.
Ziegenhain
-
Type: Traffic restrictions
-
Duration: until 19.07.2024
-
Reason: Fiber optic expansion
Ziegenhainer Straße
-
Type: Complete closure
-
Location: At house number 7
-
Start: until 19.07.2024
-
Reason: Roof work incl. crane installation
-
Details: The construction site can be passed safely on foot.
Announcements
Friedrich-Engels-Straße
-
Type: Complete closure
-
Location: Junction with Wöllnitzer Straße to junction with Kernbergstraße
-
Duration: 01.08.2024 - 27.06.2025 (overall measure)
-
Reason: Laying of media
-
1st construction phase:
01.08 - 23.12.2024
Junction of Wöllnitzer Straße to junction of Am Kochersgraben -
Details:
The detour is via Jenertal - Kernbergstraße. A detour will be signposted. The roadworks can be passed on foot.