Jena construction site report for the 2nd calendar week (08. - 14.01.2024)

05.01.2024

New closures / obstructions

Demonstration procession on Monday

  • On Monday, 08.01.2024, there may be temporary restrictions on road traffic due to a mobile demonstration procession with tractors. Exact times have not been announced by the organizers. The possible route leads from Orlamünde to Jena, via Kahla, Schöps, Jägersdorf and Ölknitz.

Demonstrations on Wednesday

  • Type: Traffic obstructions
  • Location: B7 and B88 in the direction of Jena, as well as in Jena
  • Duration: 10.01.2024, 8:00 am - 1:00 pm
  • Reason: Tractor parade
  • Details: Following the rally, obstructions on the B7 and B88 from the direction of Jena are to be expected.
  • Type: Partial closure
  • Location: Eichplatz
  • Duration: 10.01.2024, 6:00 am - 2:00 pm
  • Reason: Tractor rally
  • Details: Half of the parking lot will be closed.

Tractor parades in the city area are to be expected until approx. 1 pm. Road users are advised to allow extra time.

Unterm Sande (Leutra)

  • Type: Full road closure
  • Location: At house number 52
  • Duration: 11.01 - 19.01.2024
  • Reason: Civil engineering works
  • Details: Detour will be signposted

Finished closures

None


Existing closures

- Due to the predicted frost, there may be delays to the planned construction dates -

B7

  • Type: Half-sided closure
  • Location: between the junction Vor der Gembdenmühle and the Jena town entrance sign
  • Duration: extended until 19.01.
  • Reason: Road surface renovation incl. sidewalk construction and fiber optic expansion
  • Details: Traffic will be guided safely past the construction site by means of a mobile traffic light system.

Dammstrasse

  • Location: Magnus-Poser-Straße to Schenkstraße (1st construction phase)
  • Type: Complete closure
  • Duration: until 30.05.2024
  • Reason: Laying of pipes and renewal of the road surface
  • Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.

1st construction phase: Magnus-Poser-Straße to Schenkstraße
2nd construction phase: Schenkstraße to Charlottenstraße

Drackendorf (Am Goethepark and Am König)

  • Type: Temporary restrictions
  • Duration: Extended until 12.01.2024
  • Reason: Civil engineering work for laying fiber optic cables

Ernst-Pfeiffer-Straße

  • Type: Complete closure
  • Duration: until 01.04.2024
  • Reason: Surface course + boarding installation
  • Details: The construction site can be passed safely on foot

Grenzstraße

  • Type: Closure on one side
  • Location: At house number 2-4
  • Duration: until 01.03.2024
  • Reason: Construction of an apartment building
  • Details: Pedestrians will be guided safely past the construction site with the help of an emergency pedestrian route

Holzmarkt

  • Type: Complete closure
  • Location: At the "Roter Hirsch" inn
  • Start: 02.12.2023
  • Reason: Damage to the drinking water pipe repaired, investigation of cavities/ washouts still pending.
  • Details: The road remains closed to traffic. The buses of the lines 10, 11 and 12 of the Jenaer Nahverkehrs continue to drive a detour. Delays are to be expected.

Lobeda old town

  • Type: Temporary half-sided closure + sidewalk closure
  • Duration: extended until 01.03.2024
  • Reason: Civil engineering work for laying fiber optic cable
  • Details: The construction site can be passed safely on foot.

Lobeda East and Illmnitz

  • Type: Temporary half-sided closure + footpath closure
  • Duration: extended until 01.03.2024
  • Reason: Civil engineering work for laying fiber optic cable
  • Details: The construction site can be passed safely on foot.

Löbichauer Straße

  • Type: Complete closure
  • Location: Lower Löbichauer Straße (Karl-Liebknecht-Straße to Eschenplatz)
  • Duration: until 31.03.2024
  • Reason: Civil engineering works
  • Details: The construction site can be passed safely on foot.

Naumburger Straße

  • Type: Closure on one side
  • Duration: until 31.01.2024
  • Reason: Reconstruction of the streetcar stop + installation of track replacement
  • Details: During the construction period, a one-way street will be installed from the Zitzmannstraße junction to Altenburger Straße. The one-way street is passable in the direction of the city center. The construction site can be passed safely on foot.

Nollendorfer Straße

  • Type: Complete closure
  • Location: between Thomas-Mann-Straße and Dornburger Straße
  • Duration: until 30.05.2024
  • Reason: Major road renovation

Oberaue

  • Type: Complete closure
  • Location: From the Saaleeingang Ernst-Abbe-Sportfeld to just before the Lichtenhainer Brücke bridge
  • Duration: until 31.03.2024
  • Reason: Work on the stadium grandstand
  • Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.

Remderoda

  • Type: Complete closure
  • Location: Road in the direction of Remderoda
  • Duration: until 30.05.2024
  • Reason: Laying of drinking water pipe
  • Details: A detour via Münchenroda will be signposted.

Schroeterstraße

  • Type: Complete closure
  • Location: from the junction with Strigelstraße to the junction with Am Friedensberg
  • Duration: until 30.04.2024
  • Reason: Fundamental expansion of the road
  • Details: A second construction phase for the rest of the road is expected to follow from May 2024

Wöllnitz

  • Type: Temporary half-side closure + sidewalk closure
  • Duration: Extended until 31.05.2024
  • Reason: Civil engineering work for laying fiber optic cables
  • Details: The construction site can be passed safely on foot.

Announcements:

Naumburger Straße

  • Type: Half-sided closure
  • Location: At house number 100, junction with Flurweg and junction with Am Plan
  • Period: 15.01. - 19.01.2024
  • Reason: Inspection of the road surface
  • Details: The construction site can be passed safely on foot.