Jena construction site report for the 3rd calendar week (15 - 21.01.2024)
Unless otherwise indicated, you can get past the roadworks on foot and by bike.
New closures / obstructions
Naumburger Straße
- Type: Half-sided closure
- Location: At house number 100, junction with Flurweg and junction with Am Plan
- Period: 15.01. - 19.01.2024
- Reason: Inspection of the road surface
- Details: The construction site can be passed safely on foot.
Finished closures
B7
- Road surface renovation incl. sidewalk construction and fiber optic expansion is finished.
Drackendorf (Am Goethepark and Am König)
- Fiber optic expansion is complete.
Existing closures
Dammstraße
- Location: Magnus-Poser-Straße to Schenkstraße (1st construction phase)
- Type: Complete closure
- Duration: until 30.05.2024
- Reason: Laying of pipes and renewal of the road surface
- Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.
1st construction phase: Magnus-Poser-Straße to Schenkstraße
2nd construction phase: Schenkstraße to Charlottenstraße
Ernst-Pfeiffer-Straße
- Type: Complete closure
- Duration: until 01.04.2024
- Reason: Surface course + boarding installation
- Details: The construction site can be passed safely on foot
Grenzstraße
- Type: Closure on one side
- Location: At house number 2-4
- Duration: until 01.03.2024
- Reason: Construction of an apartment building
- Details: Pedestrians will be guided safely past the construction site with the help of an emergency pedestrian route
Holzmarkt
- Type: Complete closure
- Location: At the "Roter Hirsch" inn
- Start: 02.12.2023
- Reason: Damage to the drinking water pipe repaired, investigation of cavities/ washouts still pending.
- Details: The road remains closed to traffic. The buses of the lines 10, 11 and 12 of the Jenaer Nahverkehrs continue to drive a detour. Delays are to be expected.
Lobeda old town
- Type: Temporary half-sided closure + sidewalk closure
- Duration: extended until 01.03.2024
- Reason: Civil engineering work for laying fiber optic cable
- Details: The construction site can be passed safely on foot.
Lobeda East and Illmnitz
- Type: Temporary half-sided closure + footpath closure
- Duration: extended until 01.03.2024
- Reason: Civil engineering work for laying fiber optic cable
- Details: The construction site can be passed safely on foot.
Löbichauer Straße
- Type: Complete closure
- Location: Lower Löbichauer Straße (Karl-Liebknecht-Straße to Eschenplatz)
- Duration: until 31.03.2024
- Reason: Civil engineering works
- Details: The construction site can be passed safely on foot.
Naumburger Straße
- Type: Closure on one side
- Duration: until 31.01.2024
- Reason: Conversion of the streetcar stop + installation of track replacement
- Details: During the construction period, a one-way street will be installed from the Zitzmannstraße junction to Altenburger Straße. The one-way street is passable in the direction of the city center. The construction site can be passed safely on foot.
Nollendorfer Straße
- Type: Complete closure
- Location: between Thomas-Mann-Straße and Dornburger Straße
- Duration: until 30.05.2024
- Reason: Major road renovation
Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld to just before the Lichtenhainer Brücke bridge
- Duration: until 31.03.2024
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
Remderoda
- Type: Complete closure
- Location: Road in the direction of Remderoda
- Duration: until 30.05.2024
- Reason: Laying of drinking water pipe
- Details: A detour via Münchenroda will be signposted.
Schroeterstraße
- Type: Complete closure
- Location: from the junction with Strigelstraße to the junction with Am Friedensberg
- Duration: until 30.04.2024
- Reason: Fundamental expansion of the road
- Details: A second construction phase for the rest of the road is expected to follow from May 2024
Unterm Sande (Leutra)
- Type: Complete closure
- Location: At house number 52
- Duration: until 19.01.2024
- Reason: Civil engineering works
- Details: Detour will be signposted
Wöllnitz
- Type: Temporary half-side closure + sidewalk closure
- Duration: Extended until 31.05.2024
- Reason: Civil engineering work for laying fiber optic cables
- Details: The construction site can be passed safely on foot.
Announcements:
None