The Jena construction site report for the 52nd / 1st calendar week (23.12.2024 - 05.01.2025)

20.12.2024

Unless otherwise indicated, you can get past the roadworks on foot and by bike.

New closures / obstructions

None


Finished closures

At the brewery, passageway/underpass

  • Civil engineering works are finished.

Burgauer Weg, cycle path

  • Replacement of the sewage pressure pipes has been completed.

Dornburger Straße, southbound lane

  • Civil engineering work has been completed.

Forstweg

  • Construction of a new pressure reducing shaft for the drinking water supply has been completed.

Friedrich-Engels-Straße

  • Media laying is complete.
  • 2nd construction phase will not begin until Q1/2025

Jägerbergstraße

  • Civil engineering work is complete.

Karl-Liebknecht-Straße

  • Repair work in the road/track area has been completed.

Lichtenhainer Oberweg

  • Laying of district heating pipe is complete.

Max-Wien-Platz

  • Renovation of combined sewer is complete.

Mühlenstraße 48 - 100

  • Work on the electrical line has been completed.

Mühlenstraße 21

  • Civil engineering work has been completed.

Nollendorfer Strasse

  • Major road renovation has been completed.

Remderoda

  • Laying of drinking water pipe has been completed.

Saalebrücke, Paradies/ Rasenmühleninsel

  • Renovation work has been completed.

In front of the Neutor

  • Civil engineering work has been completed.

Existing closures

Carl-Zeiß-Platz

  • Type: Complete closure
  • Location: House numbers 12 - 14
  • Duration: until 29.08.2025
  • Reason: Renovation and new construction of the German Optical Museum

Dammstraße

  • Type: Complete closure
  • Duration: until 30.06.2025
  • Reason: Laying of pipes and renewal of the road surface
  • Details: A detour will be signposted. The construction work is divided into two construction phases:
    1st construction phase: Magnus-Poser-Straße to Schenkstraße
    2nd construction phase: Schenkstraße to Charlottenstraße

2x Dornburger Straße

  • Type: Half-sided closure + sidewalk closure
  • Location: between Nordschule and An der Eule
  • Duration: until 30.04.2025
  • Reason: Reconstruction of the streetcar catenary system
  • Type: Various closures
  • Location: House number 6
  • Start: 19.06.2024
  • Reason: New house construction
  • Addition: From 06.01.2025 to 31.07.2025, a one-way road (half-sided closure, driving direction into the city) will be set up in the area of Dornburger Straße 6. The closure will be used for loading and unloading and as a construction site facility. Out-of-town traffic will be diverted via Spitzweidenweg and Nollendorfer Straße.

Ernst-Abbe-Platz

  • Duration: until 30.04.2025
  • Reason: Construction work in the track area
  • Details: Crossing facilities for pedestrians will be set up.

Grenzstraße

  • Type: Complete closure
  • Location: Junction with Geraer Straße up to the railroad bridge
  • Duration: until 30.04.2025
  • Reason: Major roadworks
  • Details: A detour will be signposted.

Isserstedter Straße

  • Type: Complete closure
  • Location: from house number 21 to the junction with Zum Ziskauer Tal
  • Duration: The work in the entire district of Lützeroda will last until the end of 2025
  • Reason: Fundamental road expansion
  • Details: The detour will be signposted.

Kahlaische Straße, sidewalk

  • Type: Complete closure
  • Location: At house number 4 in the direction of Sandweg
  • Duration: until 30.01.2025
  • Reason: Demolition work
  • Details: The closure can be bypassed via Sandweg and Felsenkellerstraße. A detour will be signposted.

Church square

  • Type: Traffic restrictions
  • Location: Around the town church
  • Duration: until 30.05.2025
  • Reason: extensive construction work
  • Details: Access to the town church will be guaranteed during the entire construction period. Saalstraße will be fully closed for transit/delivery traffic.

Lessingstraße

  • Type: Complete closure
  • Location: between Fröbelstieg and Max-Wien-Platz
  • Duration: until 31.01.2025
  • Reason: Civil engineering works and construction site transportation
  • Details: The construction site can be bypassed via Helmholtzweg.

Löbdergraben, eastern footpath

  • Type: Complete closure
  • Location: between Steinweg and Lutherplatz
  • Duration: until 28.02.2025
  • Reason: Roadworks and media relocation
  • Details: Pedestrians will be diverted to the opposite sidewalk.

Rudolf-Breitscheid-Straße

  • Type: Complete closure
  • Location: At house numbers 8 - 30
  • Duration: until 24.04.2025
  • Reason: Reconstruction of wastewater sewer

Schroeterstraße

  • Type: Complete closure
  • Location: from Strigelstraße to Forstweg
  • Duration: until 30.05.2025
  • Reason: Fundamental road expansion
  • Details: During the construction period there is no connection to Katharinenstraße.

Wiesenstraße, traffic circle

  • Duration: until 29.11.2025
  • Reason: fundamental redesign
  • Details: Access to Kunitz and the adjacent industrial estate is only possible via Brückenstraße, but not via Wiesenstraße. A wide detour is signposted via Am Anger - Dornburger Straße - Camburger Straße. An emergency footpath to Kunitz and in the direction of Naumburger Straße leads past the roadworks.

Announcements

None