Jena construction site report for the 7th calendar week (12 - 18.02.2024)
Unless otherwise indicated, you can get past the roadworks on foot and by bike.
New closures / obstructions
Hermann-Löns-Straße
- Type: Half-time closure
- Location: at the level of the crosswalk to the junction with Mühlenstraße
- Duration: 15.02. - 31.07.2024
- Reason: Lighting and remaining work on the crosswalk
- Details: Traffic will be guided past the construction site by means of a mobile traffic light system.
Rautal
- Type: Temporary semi-permanent closure
- Location: Corner of Erich-Kuithan-Straße
- Duration: 12.02. - 16.07.2024
- Reason: Laying of medium voltage cable
- Details: Traffic will be guided past the construction site by means of mobile traffic lights.
Completed closures
Unterm Sande (Leutra)
- Civil engineering works are completed.
Existing closures
Dammstraße
- Location: Magnus-Poser-Straße to Schenkstraße (1st construction phase)
- Type: Complete closure
- Duration: until 30.05.2024
- Reason: Laying of pipes and renewal of the road surface
- Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.
1st construction phase: Magnus-Poser-Straße to Schenkstraße
2nd construction phase: Schenkstraße to Charlottenstraße
Ernst-Pfeiffer-Straße
- Type: Complete closure
- Duration: until 01.04.2024
- Reason: Surface course + boarding installation
- Details: The construction site can be passed safely on foot
Grenzstraße
- Type: Closure on one side
- Location: At house number 2-4
- Duration: until 01.03.2024
- Reason: Construction of an apartment building
- Details: Pedestrians will be guided safely past the construction site with the help of an emergency pedestrian route.
Johannisstrasse
- Type: Traffic restrictions
- Location: Eastern Johannisstraße 17-22
- Duration: until 26.04.2024
- Reason: Remaining work on laying district heating (Stadtwerke Jena)
- Details: The construction site is safe for pedestrians. Cyclists must push due to insufficient remaining width. Provided the weather cooperates, the construction work can be completed ahead of schedule at the end of March. This means that there should be as little disruption as possible for outdoor catering and visitors to the spring market.
Lobeda Old Town
- Type: Temporary half-side closure + sidewalk closure
- Duration: until 01.03.2024
- Reason: Civil engineering work for laying fiber optic cable
- Details: The construction site can be passed safely on foot.
Lobeda East and Illmnitz
- Type: Temporary half-side closure + footpath closure
- Duration: until 01.03.2024
- Reason: Civil engineering work for laying fiber optic cable
- Details: The construction site can be passed safely on foot.
Löbichauer Straße
- Type: Complete road closure
- Location: Lower Löbichauer Straße (Karl-Liebknecht-Straße to Eschenplatz)
- Duration: until 31.11.2024
- Reason: Civil engineering works
- Details: The construction site can be passed safely on foot.
Naumburger Straße
- Type: Closure on one side
- Duration: until 30.04.2024
- Reason: Conversion of the streetcar stop + installation of track replacement
- Details: During the construction period, a one-way street will be installed from the Zitzmannstraße junction to Altenburger Straße. The one-way street is passable in the direction of the city center. The construction site can be passed safely on foot.
Nollendorfer Straße
- Type: Complete closure
- Location: between Thomas-Mann-Straße and Dornburger Straße
- Duration: until 30.05.2024
- Reason: Fundamental road renovation
- Addition: In the period 07 - 13.02.2024, empty conduits will be laid in Thomas-Mann-Straße at Von-Haase-Weg. Access to Von-Haase-Weg is possible.
Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
- Duration: until 31.03.2024
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
Remderoda
- Type: Complete closure
- Location: Road in the direction of Remderoda
- Duration: until 30.05.2024
- Reason: Laying of drinking water pipe
- Details: A detour via Münchenroda will be signposted.
Schroeterstraße
- Type: Complete closure
- Location: from the junction with Strigelstraße to the junction with Am Friedensberg
- Duration: until 30.04.2024
- Reason: Fundamental expansion of the road
- Details: A second construction phase for the rest of the road is expected to follow from May 2024
Wöllnitz
- Type: Temporary half-side closure + sidewalk closure
- Duration: until 31.05.2024
- Reason: Civil engineering work for laying fiber optic cables
- Details: The construction site can be passed safely on foot.
Ziegenhain
- Type: Traffic restrictions
- Duration: until 30.03.2024
- Reason: Fiber optic expansion
Announcements:
Brückenstraße / Leibnizstraße
- Type: Half-sided closure
- Duration: 19.02. - 05.04.2024
- Reason: District heating installation
- Details: During the construction period, a one-way road closure will be installed in Brückenstraße. The one-way street is passable in the direction of Kunitz. Out-of-town traffic will be diverted via the street "Am Steinbach". The construction site can be passed safely on foot.