Jena construction site report for the 9th calendar week (26.02. - 03.03.2024)
Unless otherwise indicated, you can get past the roadworks on foot and by bike.
New closures / obstructions
Frommannstrasse
- Type: Complete closure
- Duration: 26.02. - 15.03.2024
- Reason: Road surface renovation
Cospedaer Grund
- Type: Complete closure
- Location: Height Papiermühle
- Duration: 26.02. - 29.02., 07:30 - 17:00 each day
- Reason: Traffic safety work
- Details: Residents, supply and emergency vehicles can only access Cospedaer Grund from the direction of Cospeda during the closure period. For this purpose, the concrete elements will be removed so that access is secured. Pedestrians and cyclists will be able to pass safely.
Im Steinfeld
- Type: Complete closure
- Location: At house number 12
- Duration: 26.02. - 08.03.2024
- Reason: Construction of a wastewater, electrical and drinking water house connection
Completed closures
None
Existing closures
Brückenstraße / Leibnizstraße
- Type: Half-sided closure
- Duration: 19.02. - 12.04.2024
- Reason: Laying of district heating pipe
- Details: The one-way street is passable in the direction of Kunitz. Out-of-town traffic will be diverted via the street "Am Steinbach".
Bürgelsche Straße
- Type: Temporary one-way closure
- Location: At house number 15
- Duration: 22.02. - 08.03.2024
- Reason: Civil engineering works in the sidewalk area
- Details: Traffic will be guided alternately by means of mobile traffic lights.
Dammstraße
- Location: Magnus-Poser-Straße to Schenkstraße (1st construction phase)
- Type: Complete closure
- Duration: until 30.05.2024
- Reason: Laying of pipes and renewal of the road surface
- Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.
1st construction phase: Magnus-Poser-Straße to Schenkstraße
2nd construction phase: Schenkstraße to Charlottenstraße
Ernst-Pfeiffer-Straße
- Type: Complete closure
- Duration: until 01.04.2024
- Reason: Surface course + boarding installation
- Details: The construction site can be passed safely on foot
Grenzstraße
- Type: Closure on one side
- Location: At house number 2 - 4
- Duration: until 01.03.2024
- Reason: Construction of an apartment building
- Details: Pedestrians will be guided safely past the construction site using an emergency pedestrian route.
Johannisstrasse
- Type: Traffic restrictions
- Location: Eastern Johannisstraße 17 - 22
- Duration: until 26.04.2024
- Reason: Remaining work laying district heating (Stadtwerke Jena)
- Details: The construction site can be passed safely on foot. Cyclists must push due to insufficient remaining width. Provided the weather cooperates, the construction work can be completed ahead of schedule at the end of March. This means that there should be as little disruption as possible for outdoor catering and visitors to the spring market.
Hermann-Löns-Straße
- Type: Half-sided closure
- Location: at the level of the crosswalk to the junction with Mühlenstraße
- Duration: 15.02. - 31.07.2024
- Reason: Lighting and remaining work on the crosswalk
- Details: Traffic will be guided past the construction site by means of mobile traffic lights.
Lobeda old town
- Type: Temporary half-side closure + footpath closure
- Duration: until 01.03.2024
- Reason: Civil engineering work for laying fiber optic cable
- Details: The construction site can be passed safely on foot.
Lobeda East and Illmnitz
- Type: Temporary half-side closure + footpath closure
- Duration: until 01.03.2024
- Reason: Civil engineering work for laying fiber optic cable
- Details: The construction site can be passed safely on foot.
Löbichauer Straße
- Type: Complete road closure
- Location: Lower Löbichauer Straße (Karl-Liebknecht-Straße to Eschenplatz)
- Duration: until 31.11.2024
- Reason: Civil engineering works
- Details: The construction site can be passed safely on foot.
Naumburger Straße
- Type: Closure on one side
- Duration: until 30.04.2024
- Reason: Reconstruction of the streetcar stop + installation of track replacement
- Details: During the construction period, a one-way street will be installed from the Zitzmannstraße junction to Altenburger Straße. The one-way street is passable in the direction of the city center. The construction site can be passed safely on foot.
Nollendorfer Straße
- Type: Complete closure
- Location: between Thomas-Mann-Straße and Dornburger Straße
- Duration: until 30.05.2024
- Reason: Major road renovation
Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld to just before the Lichtenhainer Brücke bridge
- Duration: until 31.03.2024
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
Rautal
- Type: Temporary half road closure
- Location: Corner of Erich-Kuithan-Straße
- Duration: 12.02. - 16.07.2024
- Reason: Laying of medium voltage cable
- Details: Traffic will be guided past the construction site by means of mobile traffic lights.
Remderoda
- Type: Complete closure
- Location: Road in the direction of Remderoda
- Duration: until 30.05.2024
- Reason: Laying of drinking water pipe
- Details: A detour via Münchenroda will be signposted.
Schroeterstraße
- Type: Complete closure
- Location: from the junction with Strigelstraße to the junction with Am Friedensberg
- Duration: until 30.04.2024
- Reason: Fundamental expansion of the road
- Details: A second construction phase for the rest of the road is expected to follow from May 2024
Wöllnitz
- Type: Temporary half-side closure + sidewalk closure
- Duration: until 31.05.2024
- Reason: Civil engineering work for laying fiber optic cables
- Details: The construction site can be passed safely on foot.
Ziegenhain
- Type: Traffic restrictions
- Duration: until 30.03.2024
- Reason: Fiber optic expansion
Announcements
Fritz-Reuter-Straße
- Type: Full road closures in sections
- Duration: 04.03 - 12.04.2024
- Reason: Reconstruction of the combined sewer
Saalstraße / western sidewalk in Löbdergraben
- Type: Traffic restrictions
- Duration: 04.03 - 15.03.2024
- Reason: Laying of media
- Details: Pedestrians can safely pass the construction site in Saalstraße