Complete closure of Winzerlaer Straße / Rudolstädter Straße ended early
The construction work in the Winzerlaer Straße / Rudolstädter Straße area was completed earlier than planned. The work originally scheduled for the period from 04.05.2026 to 29.05.2026 ended today, on 21.05.2026. The route was immediately reopened to traffic.
During the construction period, work was carried out on the track system there. The detour set up for private traffic via Rudolstädter Straße and Hermann-Löns-Straße has already been lifted.
The temporary changes to local public transport services have also been discontinued. Streetcar line 2 and bus line 10 are running regularly again.
We wish all road users a safe and smooth journey.