The construction site report for the 16th calendar week of 2019

11.04.2019

The roadworks report for the 16th calendar week of 2019 - detours are signposted, pedestrians pass the roadworks.

  • Grietgasse / corner of Neugasse
    Construction work has already been completed.
  • Full closures Burgweg 60
    Crane assembly is complete
  • Half-sided closure Am Anger 32
    However, the closure must be reactivated at the end of April 2019 in order to connect the electrical connections.

  • Karl-Liebknecht-Straße construction site
    During the vacation period from 12.04.2019 to 27.04.2019, streetcar line 2 will be interrupted. It will only run from the city center to the construction site. The streetcar will also run between the Jenzigweg stop and the final stop in Jena-Ost.
  • Half-sided closure of Schlippenstraße
    From 15.04.2019 to 24.04.2019, there will be a half-sided road closure in the area of Schlippenstraße 15-19. The closure is necessary to disconnect a house connection.
  • Full road closure Tümplingstraße 31
    In the period from 15.04.2019 to 23.04.2019, the service pipes at the property at Tümplingstraße 31 will be renewed. During this time, the road will be closed to vehicle traffic. The construction site can be bypassed locally via the adjacent roads.
  • Complete closure of Karl-Liebknecht-Straße
    Stadtwerke will be laying a new combined sewer in the area between Brändströmstraße and Pestalozzistraße until around 31.05.2019. During this time, Karl-Liebknecht-Straße will be closed to traffic in the construction site area.
    completely closed to vehicle traffic.

    During the vacation period from 12.04.2019 to 27.04.2019, streetcar line 2 will also be interrupted. It will only run from the city center to the construction site. The streetcar will also run between the Jenzigweg stop and the final stop in Jena-Ost.

    The major traffic detour will take place in both directions via Jenzigweg and Wiesenstraße to the Anger junction. The traffic light control at the Anger junction is to be optimized. However, residents can also bypass the roadworks via Am Steinborn and Löbichauer Straße. Temporary stopping restrictions will be put in place along this route to help traffic flow

  • Closure of Naumburger Straße / Rautal
    The Naumburger Straße / Am Steinbach junction is fully closed. The large-scale detour is via Brückenstraße - Wiesenstraße - Am Anger and back.

    Despite the barriers in Brückenstraße: Please do not attempt to drive through the residential area! Public and school buses drive through the small streets. "Creeping traffic" would massively obstruct local traffic there. In addition, the sidewalks are partially separated from the carriageway - the safety of school routes has top priority.

    We would like to thank all considerate drivers!

    Another note for pedestrians and cyclists: The footpaths in the area of the entire construction site can be used throughout this year.

  • Traffic obstructions at the Mühlenstraße / Hermann-Löns-Straße junction
    Construction work has currently begun in the intersection area and will continue until 26.04.2019. During the construction work in the intersection area, electrical cables will be laid in the sidewalk area of the intersection. During the work, traffic will have to be controlled by traffic lights. This will result in traffic obstructions on Hermann-Löns-Straße.

  • Complete closure of Lichtenhainer Oberweg between the Carl-Zeiss-Promenade junction and the junction with Döbereinerstrasse
    A full road closure will be implemented in the above-mentioned area from 01.04.2019 to 28.06.2019. During the closure period, traffic will be diverted via the adjacent streets Phillip-Müller-Straße; Döbereinerstraße; Friedrich-Körner-Straße. The detour is signposted.

  • Construction work on Camburger Straße continues
    The construction work to replace the drinking water pipes in Camburger Straße, which began in 2018, is continuing and is scheduled to last until the end of June 2019. During the construction period, traffic heading towards the city center will remain on Camburger Straße. As last year, northbound traffic will be routed back to Camburger Straße via Spitzweidenweg and Scharnhorststraße.

  • Complete closure of Schillstraße 1
    Schillstraße will be closed from 08.04.2019 to 31.05.2019 because the sewer and house connections have to be renewed in this area. Road traffic will be diverted locally and the detour will be signposted.

  • Moritz- von Rohr-Straße
    Repair work is required on the district heating pipe at the junction of Moritz-von-Rohr-Straße and Lichtenhainer Straße. The road will be closed on one side from 04.04.2019 to 30.04.2019.

  • Am Steinborn 35
    In the area of Am Steinborn 35, there will be a half-sided road closure from 09.04.2019 to 18.04.2019. The narrowing is required as construction space for work on the drainage pipe.

  • Full closure of Mittelstraße
    From 08.04.2019 to 30.08.2019, the sewer will be renewed in Mittelstraße between Otto-Schott-Straße and Kronfeldstraße. This section of road will be completely closed to vehicle trafficfor the milling of the road surface . Afterwards, a section-by-section full closure in the immediate work area will be necessary. It is possible to drive around the construction site via the adjacent roads.

  • Narrowing of Am Eisenbahndamm road
    In the period from 25.03.2019 to 26.07.2019, a drinking water pipeline will be laid through the railroad embankment between Landveste and Straße am Eisenbahndamm on behalf of the municipal utilities. During this construction work, the cycle/walking path will be closed in the area of the construction site at Landveste and rerouted in the area of Landveste. There will also be a temporary narrowing of the road Am Eisenbahndamm, especially at times when traffic is lighter, as one of the two left-turn lanes in the direction of Paradiesbrücke (Stadtrodaer Straße) will have to be shortened slightly.
  • Traffic obstructions at the Mühlenstraße / Hermann-Löns-Straße junction
    Construction work has currently begun in the intersection area and will continue until 26.04.2019. During the construction work in the intersection area, electrical cables will be laid in the sidewalk area of the intersection. During the work, traffic will have to be controlled by traffic lights. This will result in traffic obstructions on Hermann-Löns-Straße.
  • Complete closure of Rautalstraße
    From 25.03.2019, Rautalstraße between Kuithanstraße and Ottogerd-Mühlmann-Straße will be closed to vehicle traffic. The detour will be via Kuithanstraße, Zitzmann-Straße, Straße and Ottogerd-Mühlmann-Straße or G.-Neumann-Straße. The closure is expected to last until mid-May 2019. After that, the Rautal area between Ottogerd-Mühlmann-Straße and Jägerbergstraße will be closed and traffic will be diverted via Closewitzer Straße. This section is scheduled to be reopened to traffic on 05.07.2019.
    During the closure period, a new drinking water pipe will be laid in Rautal.
    In the fall of this year, this new drinking water pipeline is to be laid further along the Rautal to the end of Jena in the direction of Closewitz.
  • Maria-Pawlowna-Straße
    In the period from 11.03.2019 to 07.06.2019, the road will be closed to vehicle traffic due to construction work on the district heating pipeline. Traffic between Naumburger Straße and Schreckenbachweg or Am Rosenhang will be diverted in both directions via Flurweg.
  • Bachstraße
    Bachstraße will be closed on one side from 01.11.2018 to 25.04.2019 in the area of house no. 15. During the closure period, scaffolding will be erected there, which will restrict road traffic.
  • Max-Wien-Platz
    The property at Philosophenweg 26 is being built on. For this reason, it will be necessary to restrict traffic in the area where Kritzegraben joins Philosophenweg. In order not to divert traffic, a traffic light system will regulate traffic at this junction. The traffic restriction will end in the middle of 2019
  • Closure of Marktstraße in Lobeda-Altstadt
    Construction work for the further expansion of Marktstraße between Marktplatz and Nikolaus-Theiner-Straße and further via Lobdeburgweg between Stadtgraben and Spitzbergstraße until 27.09.2019 - road closures in sections.
  • Leutra
    A sewer will be laid in Leutra between 04.03.2019 and 26.04.2019. The road will be closed on one side during the construction period. The construction work will be carried out in several sections one after the other in order to keep traffic disruptions to a minimum.
  • Jena Spring Market
    Due to the Jena Spring Market, the town hall parking lot and Eichplatz will be closed for parking from May 6, 2019 to May 20, 2019. The e-charging station on Eichplatz can still be used. Access is from Kollegiengasse. During the Jena Spring Market, the delivery time for the pedestrian zone Altstadt will be limited to the time between 06:00 and 12:00.
  • Beutnitzer Straße 1
    Beutnitzer Straße will be closed to through traffic from 23.04.2019 to 26.04.2019. Beutnitzer Straße will be a dead end for vehicles during the construction period.