Construction site report for the 24th calendar week of 2019

07.06.2019

Complete closure of Stadtrodaer Straße in Lobeda
Work completed

Section of Rautalstraße
Construction section between Kuithanstraße and Ottogerd-Mühlmann-Straße completed

Dornburger Straße / Scharnhorststraße
No more traffic restrictions

Maria-Pawlowna-Straße
Construction work for district heating pipes is finished

Where What Why When Hints

Rautalstrasse

Construction phase

closed between the junction with Am Heiligenberg and the junction with Closewitzer Straße

Laying of drinking water pipe

The civil engineering work will then begin on 11.06.2019, 08:00 a.m., and will continue until 16.08.2019.

A detour in the direction of Closewitz will be signposted

Ilmstraße 16 to 18

Closure Crane work

08.04.2019 until 14.06.2019

Ilmstraße is marked as a dead end at both entrances and is passable up to the construction site.

Where What Why When Hints
Bernhard-Schultze-Straße Complete closure

between Am Steinborn and the junction with Julius-Schaxel-Straße

Civil engineering work on supply lines until 27.08 Crossing and turning over the tracks is not possible.
Camburger Straße Closure on one side Laying of gas pipes until 15.06. During the construction period, road traffic in the direction of the city center will remain on Camburger Straße. As last year, northbound traffic will be routed back to Camburger Straße via Spitzweidenweg and Scharnhorststraße.
Railroad
dam
Narrowing of the road Laying of a drinking water pipe through the railroad embankment between the Landveste and the road along the railroad embankment until 26.07 During the construction work, the cycle/walking path will be closed in the area of the construction site at Landveste and rerouted in the area of Landveste. There will also be a temporary narrowing of the road Am Eisenbahndamm, especially at times when traffic is lighter, as one of the two left-turn lanes in the direction of Paradiesbrücke (Stadtrodaer Straße) will have to be shortened slightly.
Lichtenhainer Oberweg Full closure between Carl-Zeiss-Promenade and Döbereinerstrasse until 28.06.

Detour via the adjacent streets Phillip-Müller-Straße; Döbereinerstraße; Friedrich-Körner-Straße.

Lutherplatz/ Inselplatz Closure of approx. 1/3 of the parking lot Archaeological excavations until 20.09
Marktstraße in Lobeda-Altstadt Closure in sections Extension of Marktstraße between Marktplatz and Nikolaus-Theiner-Straße and further via Lobdeburgweg between Stadtgraben and Spitzbergstraße until 27.09.
Max-Wien-Platz Restrictions in the area where Kritzegraben joins Philosophenweg Development of the property at Am Philosophenweg 26 until mid-2019 Construction site traffic lights regulate traffic.
Mittelstraße Complete closure Replacement of the sewer between Otto-Schott-Straße and Kronfeldstraße until 30.08. It is possible to drive around the construction site via the adjacent roads.
Naumburger Straße / Rautal Full closure of the Naumburger Straße / Am Steinbach junction Extension of Naumburger Straße between Camburger Straße and Flurweg

Large-scale detour via Brückenstraße - Wiesenstraße - Am Anger and back.

Despite the barriers in Brückenstraße: Please do not attempt to drive through the residential area! Public and school buses drive through the small streets. "Creeping traffic" would massively obstruct local traffic there. In addition, the sidewalks are partially separated from the carriageway - the safety of school routes has top priority.

Schillstrasse 1 Complete closure Replacement of sewer and house connections until 14.06. Traffic will be diverted locally.
Schrödingerstr. 8-18 Half-sided closure Renovation work on the adjacent building until 08.11.
Stifterstrasse Full closure Laying of a new drinking water pipe until 31.07.
Am Volksbad Half-sided closure Construction of a footpath incl. ancillary facilities at the bus station until 26.06. The street Am Volksbad is only accessible from Grietgasse in the direction of Knebelstraße.

Westbahnhofstraße between house numbers 2a and 6a

In the course of the retaining wall renovation, a half-sided closure will be installed. The closure is planned for the period from 17.06.2019 to 29.09.2019. If the construction work causes traffic jams for traffic heading into the city, the construction site can be bypassed via Rathenaustraße - Curt-Unckel-Straße - Hainstraße and An der Brauerei.