Construction site report week 37 (12.09. - 18.09.2022)
Here is the current roadworks report for the 37th calendar week of 2022.
Unless otherwise stated, cyclists and pedestrians will pass the roadworks.
FINISHED CONSTRUCTION SITES
Löbdergraben stops (university main building)
- Cutting work is finished.
Saalbahnhofstraße stop (Spittelplatz)
- Cutting work is finished.
Naumburger Straße at the junction with Brückenstraße
- Civil engineering works have been completed.
Wiesenstraße
- Civil engineering works have been completed.
NEW CONSTRUCTION SITES / CLOSURES
Construction work at the final stop in Erlanger Allee / Carolinenstraße
- Type: Complete closure
- Duration: 13.09. - 16.12.2022
Käthe-Kollwitz-Straße
- Type: Complete closure
- Location: Lane in the direction of Saalbahnhofstraße and adjacent lanes
- Duration: 12.09. - 29.10.2022
- Reason: Civil engineering works
- Details: Traffic will be diverted via the adjacent road network
Church square
- Type: Complete closure
- Location: Lane in the direction of Saalbahnhofstraße, as well as adjacent
- Duration: 13.09. - 14.09.2022
- Reason: Crane work
- Details: Pedestrians and cyclists can pass the construction site safely.
Unterm Sande (Maua)
- Type: Complete closure
- Location: At house number 36
- Duration: 12.09. - 23.09.2022
- Reason: Civil engineering works
- Details: Traffic will be diverted via Im Semmicht road.
EXISTING CONSTRUCTION SITES
Library square
- Type: One-way traffic regulation in the direction of Damenviertel
- Duration: until 16.09.2022
- Reason: Laying of fiber optic cable for THULB
Buchenweg
- Type: Half-sided closure
- Place: House number 34
- Duration: until 12.10.2022
- Reason: Construction site installation for the conversion of the adjacent school
- Details: Waiting is mandatory for vehicles meeting in the carriageway area.
Carolinenstrasse
- Type: Complete closure
- Duration: until 14.10.2022
- Reason: Pavement renovation
- Details: The construction work will be divided into several construction phases so that access for residents/rescue and supply services is guaranteed. A detour will be signposted on site. Pedestrians and cyclists can pass the construction site safely.
Eichplatz (parking lot)
- Type: Partial closure
- Duration: until 04.12.2022
- Reason: Carrying out archaeological investigations in advance of the development of construction site A
- Details: In order to carry out the work professionally, restrictions on the parking lotare unavoidablefor a period of approx. five months. However, high priority will be given to ensuring that as many parking spaces and pathways as possible are maintained during the work. For this reason, the excavations will be carried out in three successive sections, as shown in the plan below.
We would also like to point out that the usual main access to Eichplatz via Kollegiengasse will not be available during this period. However, the directly adjacent temporary access road can be used asan alternative to entering the parking lot .In addition, one of the tworamps leadingfrom the parking lot to the "Neue Mitte" willno longer be available. However, the second ramp is still available without restriction.
The excavation work is usually carried out Monday to Friday from 7 am to 4 pm.
We will provide up-to-date information on the construction work and any associated restrictions or time changes on the website www.eichplatzareal.de .
Engelplatz
- Type: Half-sided closure
- Duration: until 07.10.2022
- Reason: Laying of medium voltage cables for the new library
- Details: Traffic will be routed in a one-way system in the direction of Schillerstraße
Felsenkellerstrasse
- Type: Complete closure
- Location: Houses 9 -11
- Duration: until 30.09.2022
- Reason: extensive construction work
- Details: A detour will be signposted on site. Pedestrians and cyclists can pass the construction site safely.
Forest road
- Type: Closure on one side
- Location: At house number 35a
- Duration: until 31.12.2022
- Reason: New construction of a residential building
Friedrich-Körner-Straße / Ernst-Pfeiffer-Straße
- Type: Complete closure
- Duration: until 17.09.2022
- Reason: Civil engineering works
- Details: During the construction period (1st construction phase), Friedrich-Körner-Straße will be fully closed. ernst-Pfeiffer-Straße will then also be fully closed. A detour will be signposted on site. Pedestrians can pass the construction site safely.
Gerbergasse
- Type: Closure of residents' parking lot
- Start: 25.04.2022
- Reason: Construction site installation
- Details: Alternative residents' parking spaces have been set up in Wiesenstraße from the Am Saaleufer access road. These can be used immediately.
Julius-Schaxel-Straße
- Type: Complete closure
- Duration: until 31.12.2022
- Reason: Road expansion incl. pipe laying
- Details: Pedestrians can pass the construction site safely. There will be 3 construction phases. Construction phases 2 + 3 will not take place until 2023.
Kochstraße
- Type: Complete closure
- Location: House number 4 to the junction with Forstweg
- Duration: until 28.10.2022
- Reason: Civil engineering works
- Details: Access/exit to the daycare center and day clinic is possible from Westbahnhofstraße
Lobeda-Altstadt - Neulobeda - Drackendorf
- Type: Restrictions
- Duration: until approx. 30.09.2022
- Reason: Civil engineering work for laying fiber optic cable
Löbdergraben
- Type: Complete closure
- Location: Junction with Paradiesstraße to the level of Ludwig-Weimar-Gasse
- Duration: until 16.09.2022
- Reason: Laying of media (backbone network)
- Details: Commercial delivery traffic and regular services can travel along the construction site. Other traffic will be diverted via the adjacent road network.
Naumburger Straße in the Schützenhofstr. / Altenburger Str. area
- Type: Complete closure
- Location: Naumburger Str. / Schützenhofstr./Altenburger Str. intersection area
- Duration: until 17.10.2022
- Reason:Repair of the district heating pipeline for Jena Nord
- Details: Traffic will be diverted via Scharnhorststr. / Camburger Str.
Eastern Löbdergraben
- Type: Half-sided closure
- Location: Height Saalstraße
- Duration: until 31.10.2022
- Reason: Installation of a construction site exit
- Details: Pedestrians can still pass through the area
Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
- Duration: until 31.03.2023
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
Oberaue from the southern access road to the main access road at Stadtrodaer Straße
- Type: Complete closure
- Duration: until 31.12.2022
- Reason: Fundamental expansion of the access road, expansion and widening of the main cycle path connection
- Detour: A designated detour route will be set up for cyclists heading into and out of the city. The cycle routes run via Wöllnitzer Straße and Burgauer Weg.
- Restrictions for swimmers accessing Südbad/Schleichersee and the beach bar as well as for adjacent sports facility users: The facilities will be accessible from the main stadium access road via a temporary footpath. This footpath can only be used by pedestrians - cyclists must dismount.
Guests of the Schleichersee and the adjacent sports facilities as well as the traffic school with cars can use the parking lot in the Oberaue directly next to the main access road. This is only not possible when FC Carl Zeiss Jena is playing at home. A planning board will be set up at the main entrance to the Oberaue so that road users are informed.
Thomas-Münzer-Weg
- Type: Complete closure
- Place: House number House number 4
- Duration: until 30.06.2023
- Reason: Construction of a residential building
- Details: The full closure is indicated by means of planning boards from both Jägerbergstraße and Max-Gräfe-Gasse. A wide detour must be taken around the closed area. Pedestrians and cyclists can pass the construction site safely.
Tieckstraße
- Type: Half-sided closure
- Duration: until 16.09.2022
- Reason: Installation of telecommunication lines
- Details: A one-way street will be set up for this purpose. As the construction work will also affect the entire pavement, a temporary traffic-calmed area will be installed so that pedestrians and other road users will have to use it. Access to the adjacent apartment blocks will be made possible
Change to the one-way street layout in Unterdorfstraße and Wöllnitzer Oberweg
- Type: Full closure
- Location: Unterdorfstraße 2
- Duration: until 31.12.2022
- Reason: Construction work
- Details: The one-way street layout will be changed in the above-mentioned streets. In Unterdorfstraße, it will then be possible to drive out of the city and in Wöllnitzer Oberweg, it will be possible to drive into the city. Cyclists will be able to ride against the one-way street in Wöllnitzer Oberweg. Signage will be put up at the start of the construction work to raise road users' awareness.
Wenigenjenaer Ufer
- Type: Complete closure
- Location: At house number 17 b to the junction with Tümplingstraße
- Duration: until 30.09.2022
- Reason: Renewal of the combined sewer
- Details: The construction work will be divided into 2 construction phases. A detour will be signposted.
- 2nd construction phase: House number 15-17 b
- 1st construction phase: Tümplingstraße up to house number 15
Westbahnhofstraße
- Type: Half-sided closure
- Location: at Kochstraße level
- Duration: until 16.09.2022
- Reason : Connection of the sewage pipe from Kochstraße to Westbahnhofstraße
- Details: Traffic can drive alternately by means of construction site traffic lights.
Ziegenhainer Straße
- Type: Complete closure
- Location: House number 7a
- Duration: until 31.12.2022
- Reason: New house construction
- Details: Properties in the direction of Burgweg can be reached via this road. Pedestrians can pass the construction site safely.
Zum Ziskauer Tal (Lützeroda)
- Type: Complete closure
- Duration: until 21.12.2022
- Reason : Civil engineering works (sewage; drinking water)
- Details: A detour will be signposted on site.
ANNOUNCEMENT
Erlanger Allee
- Type: Complete closure
- Duration: 19.09. - 22.10.2022
- Reason: Work on the tracks
- Details: A detour will be signposted on site. Pedestrians can pass the area safely.