The construction site report for week 13 (27.03. - 02.04.2023)
Here is the current roadworks report for the 13th calendar week (27.03 - 02.04.2023).
Unless otherwise stated, you can walk or cycle past the roadworks.
FINISHED CONSTRUCTION SITES
Berthold-Delbrück-Straße
- Half-sided closure is finished.
Camsdorfer Bridge
- Partial closure has ended.
Fürstengraben
- Partial closure has been completed.
Löbichauer Straße
- Full closure has been completed.
Closure of Mühlenstraße level crossing
- Full closure ends on 26.03.2023 (6:00 am)
Saarbrücker Straße
- Complete closure is finished.
Wehrgasse
- Complete closure is finished.
NEW CONSTRUCTION SITES / CLOSURES
Sidewalk Kahlaische Straße
- Type: Complete closure
- Location: Height Kotschauweg 2
- Duration: 27.03.2023 to 21.04.2023
- Reason: Work on the retaining wall
- Details: Pedestrians must avoid the sidewalk on weekdays from 8:00 - 16:00 via Burgauer Weg.
Martin-Niemöller-Straße
- Type: Complete closure
- Location: At house number 4
- Duration: 28.03.2023 to 31.03.2023
- Reason: Civil engineering works
- Details: The construction site can be bypassed via the adjacent road network. Pedestrians can pass the construction site safely.
Spitzweidenweg
- Type: Closure on one side
- Location: from the junction with Scharnhorststraße to the old goods station
- Duration: 27.03.2023 to 28.04.2023
- Reason: Civil engineering works
- Details: Traffic will be guided past the construction site by means of one-way traffic control (direction of travel into the city). Pedestrians can pass the construction site safely.
EXISTING CONSTRUCTION SITES
Library square
- Type: Half-sided closure
- Duration: until 27.03.2023
- Reason: Expansion of backbone network
- Details: Traffic will be closed in the northbound direction (Damenviertel). Cycle traffic is not affected by the closure.
Buchenweg
- Type: Closure on one side
- Location: House number 34
- Duration: until 30.07.2023
- Reason: Construction site installation for the conversion of the adjacent school
- Details: Waiting is mandatory for vehicles meeting in the carriageway area.
Carl-Zeiss-Promenade
- Type: Half-sided closure
- Location: Level with the university of applied sciences
- Duration: until 30.04.2023
- Reason: Electrical connection for a billboard
Erlanger Allee - cycle path connection between Lobeda-Ost and Lobeda-West
- Type: Closure of partial areas and path connections
- Location: between Theobald-Renner-Str. and Kastanienstraße junction and in the opposite direction
- Duration: until 29.02.2024
- Reason: Construction of a cycle path connection
- Details: In the first construction phase, the carriageway will be closed on one side and the pedestrian crossing at Platanenstraße to Paul-Schneider-Straße will be fully closed. Furthermore, from 27.03.2023 to 14.04.2023, the adjacent footpath/cycle path will be fully closed. A detour for pedestrians and cyclists will be signposted on site.
Gotthard-Neumann-Straße
- Type: Complete closure
- Location: Junction with Jenergasse to Johannisstaße 17
- Duration: until 21.04.2023
- Reason: Work on the district heating pipeline
- Details: The construction site can be passed on foot.
Johannisstrasse
- Type: Restrictions
- Location: Junction with Jenergasse to Johannisstaße 17
- Duration: until 05.05.2023
- Reason: Laying of media
- Details: The construction site can be passed on foot. Cyclists must dismount during the construction period.
Julius-Schaxel-Straße
- Type: Complete closure
- Duration: until 31.08.2023
- Reason: Road expansion incl. pipe laying
- Details: The construction site can be passed on foot.
Lessingstraße
- Type: Complete closure
- Location: House number 8-10
- Duration: until 26.05.2023
- Reason: Laying of drinking water pipe
- Details: From 13.03.23 to 26.05.23 Lessingstraße is not accessible from the direction of Am Steiger. Fröbelstieg can only be approached from Philosophenweg.
Lindenhöhe
- Type: Complete closure
- Duration: until 05.05.2023
- Reason: Civil engineering works
- Details: The construction site can be passed safely on foot.
Lutherplatz
- Type: Closure of one lane in the westbound direction (Fürstengraben)
- Duration: until 31.03.2023
- Reason: Expansion of the backbone network
- Details: Traffic from Wiesenstraße and Am Anger can only use the three lanes again immediately before the Löbdergraben junction.Pedestrians will be guided past the construction site and access to Lutherplatz 3 will remain possible.
Drackendorf
- Type: Temporary restrictions
- Duration: until 28.04.2022
- Reason: Civil engineering work for laying fiber optic cable
Max-Gräfe-Gasse
- Type: Partial closure
- Location: Corner of Kreuzgasse
- Duration: until 31.03.2023
- Reason: Construction site installation for house conversion
- Details: The construction site can be passed.
Münchenrodaer Grund
- Type: Half-sided closure
- Duration: until 27.03.2023
- Reason: Tree maintenance work
- Details : Traffic will be guided past the roadworks using mobile traffic lights.
2X Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
- Duration: until 30.07.2023
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
- Type: Closure of partial areas
- Location: From the main stadium access road to Roland-Ducke-Weg
- Duration: until 04.08.2023
- Reason: Expansion of the road and ancillary facilities
- Details: Access to the Oberaue will always be possible. In the first construction phase, work is currently underway from the main stadium access road to just before the Roland-Ducke-Weg junction. The construction site can be passed, but obstructions are to be expected. Cyclists can bypass the construction site safely and quickly. A detour has been set up and signposted for this purpose.
Schützenhofstraße
- Type: Closure on one side
- Location: from lower Closewitzer Straße to the level of Schützenhofstr. 66
- Duration: until 28.04.2023
- Reason: Civil engineering works
- Details: Pedestrians will be guided safely past the construction site. Cyclists must dismount during the construction period.
Thomas-Münzer-Weg
- Type: Complete closure
- Location: House number 4
- Duration: until 30.06.2023
- Reason: Construction of a residential building
- Details: The full closure is indicated by means of planning boards from both Jägerbergstraße and Max-Gräfe-Gasse. The restricted area must be driven around extensively. The construction site can be safely passed on foot and by bike.
To the Ziskauer Valley (Lützeroda)
- Type: Complete closure
- Duration: until 28.04.2023
- Reason : Civil engineering works (sewage; drinking water)
- Details: A detour will be signposted on site.
ANNOUNCEMENT
Dammstraße
- Type: Complete closure
- Duration: expected from 03.04.2023
- Reason: Renewal of pipelines and traffic facilities
- Details: The construction work is divided into two construction phases. The construction site can be passed on foot. A detour for private traffic will be signposted on site.
1st construction phase: Magnus-Poser-Straße to Schenkstraße
2nd construction phase: Schenkstraße to Charlottenstraße
Burgau track triangle
- Type: Complete closure
- Duration: 03.04.2023 to 06.04.2023
- Reason: Work on the track system
- Details: The full closure can be bypassed via the adjacent footpath/cycle path. A detour will be signposted on site.
Keßlerstraße
- Type: temporary lane closure
- Location: At petrol station level
- Duration: 11.04.2023 to 23.04.2023
- Reason: Work on the track system
- Details: The construction site can be passed on foot and by bike. A detour for private traffic will be signposted on site.