The construction site report for week 19 (08.- 14.05.2023)
Here is the current roadworks report for the 19th calendar week (08 - 14.05.2023).
Unless otherwise stated, you can walk or cycle past the construction sites.
FINISHED CONSTRUCTION SITES
Johannisstrasse
- Media has been laid.
NEW CONSTRUCTION SITES / ROAD CLOSURES
Ernst-Haeckel-Straße
- Type: Complete closure
- Duration: 08.05.2023 to 15.07.2023
- Reason: Renewal of the sewer
- Details: Traffic will be diverted via Knebelstraße/ Am Eisenbahndamm or via Magdelstieg/ Tatzendpromenade.
Lützeroda
- Type: Temporary restrictions
- Duration: 08.05.2023 to 17.07.2023
- Reason: Civil engineering work for laying fiber optic cables
Schützenhofstraße
- Type: Complete closure
- Location: At the junction with Munketal
- Duration: 04.05.2023 to 30.06.2023
- Reason: Accident
- Details: Traffic will be diverted. From 04.05.2023, the buses of line 15 of the Jenaer Nahverkehrs will run via the northern Schützenhofstraße. Delays are to be expected along the route. In addition, it is urgently requested that cars are not parked in Schützenhofstraße, even if the signposted stopping ban does not apply until Monday, 08.05.2023, so as not to obstruct bus traffic.
EXISTING ROADWORKS
Buchenweg
- Type: Half-sided closure
- Location House number 34
- Duration: until 30.07.2023
- Reason: Construction site installation for the conversion of the adjacent school
- Details: Waiting is mandatory for vehicles meeting in the carriageway area.
Carl-Zeiss-Promenade
- Type: Half-sided closure
- Location: At bridge level
- Duration: until 19.05.2023
- Reason: Civil engineering works
- Details: Pedestrians and cyclists can pass the construction site safely.
Drackendorf
- Type: Temporary restrictions
- Duration: until 30.06.2022
- Reason: Civil engineering work for laying fiber optic cable
Dammstraße
- Location: Magnus-Poser-Straße to Schenkstraße (1st construction phase)
- Type: Complete closure
- Duration: until 30.05.2024
- Reason: Line and traffic system renewal
- Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.
1st construction phase: Magnus-Poser-Straße to Schenkstraße
2nd construction phase: Schenkstraße to Charlottenstraße
Erlanger Allee - cycle path connection between Lobeda-Ost and Lobeda-West
- Type: Closure of sections and path connections
- Location: between Theobald-Renner-Str. and Kastanienstraße junction and in the opposite direction
- Duration: until 29.02.2024
- Reason: Construction of a cycle path connection
- Details: In the first construction phase, the carriageway will be closed on one side and the pedestrian crossing at Platanenstraße to Paul-Schneider-Straße will be fully closed.
Erlanger Allee (bus stop Uni-Klinikum out of town)
- Type: Half-sided closure
- Duration: until 16.06.2023
- Reason: Renewal of the bus stop
- Details: The replacement bus stop will be located in the immediate vicinity. Congestion is to be expected as there is a lane narrowing. Pedestrians and cyclists can pass the construction site safely.
Sidewalk closure from Lutherplatz/corner of Saalbahnhofstraße to Dornburger Str. 52
- Duration: until 14.07.2023
- Reason: Installation/conversion of catenary masts
- Details: For the most part, pedestrians can pass the construction site safely. If the pavement is completely closed, pedestrians and cyclists will be diverted accordingly. The construction work will begin on 02.05.2023 at Lutherplatz / corner of Saalbahnhofstraße and end on 14.07.2023 at Dornburger Straße 52.
Julius-Schaxel-Straße
- Type: Complete closure
- Duration: until 31.08.2023
- Reason: Road expansion incl. pipe laying
- Details: The construction site can be passed on foot.
Keßlerstraße
- Type: Closure on one side
- Location: At house numbers 11 and 15
- Duration: until 10.05.2023
- Reason: Civil engineering works
- Details: Pedestrians are safely guided to the opposite side of the footpath by means of barriers.
Laasan
- Type: Temporary restrictions
- Duration: until 16.06.2023
- Reason: Civil engineering work for laying fiber optic cables
- Details: Due to the laying of fiber optic cables commissioned by Deutsche Telekom, half-sided road closures and local full closures must be expected.
Lessingstraße
- Type: Complete closure
- Duration: until 26.05.2023
- Reason: Civil engineering works
- Details: During the construction period, Lessingstraße is not accessible from the direction of Am Steiger. Fröbelstieg can only be accessed from the direction of Philosophenweg.
Lindenhöhe
- Type: Complete closure
- Duration: until 15.05.2023
- Reason: Civil engineering works
- Details: The construction site can be safely passed on foot.
2x Oberaue
- Type: Complete closure
- Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
- Duration: until 30.07.2023
- Reason: Work on the stadium grandstand
- Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
- Type: Closure of partial areas
- Location: From the main stadium access road to Roland-Ducke-Weg
- Duration: until 04.08.2023
- Reason: Expansion of the road and ancillary facilities
- Details: Access to the Oberaue will always be possible. In the first construction phase, work is currently underway from the main stadium access road to just before the Roland-Ducke-Weg junction. The construction site can be passed, but obstructions are to be expected. Cyclists can bypass the construction site safely and quickly. A detour has been set up and signposted for this purpose.
- In the 2nd construction phase from 24.04.2023, the main access road to the stadium will be closed on one side. Traffic will be guided alternately by a mobile traffic light system.
Thomas-Münzer-Weg
- Type: Complete closure
- Location House number 4
- Duration: until 30.06.2023
- Reason: Construction of a residential building
- Details: The full closure is indicated by means of planning boards from both Jägerbergstraße and Max-Gräfe-Gasse. The restricted area must be driven around extensively. The construction site can be safely passed on foot and by bike.
Unterm Sande (Maua)
- Type: Half-sided closure
- Duration: until 19.05.2023
- Reason: Cable laying
Ziegenhainer Straße
- Type: Full closure
- Place: House number 99
- Duration: until 12.05.2023
- Reason: Media relocation
- Details: A detour will be signposted on site. Pedestrians and cyclists can pass the bus stop safely.
Access to Gemdental
- Type: Complete closure
- Location: Access to Gemdental road (Gemdental / Am Jenzig / Am Erlkönig junction)
- Duration: until 09.06.2023
- Reason: Development of the local heating network for the "Erlenhöfe" residential area
- Details: Residents can reach Gemdental street via Karl-Liebknecht-Straße and an additional path to Am Jenzig street will be upgraded. A detour for the church cycle path will be signposted. Please see the attachment for information on access to the Talstein nursery.
Access regulations for the Talstein nursery
© Kommunalservice Jena
To the Ziskauer valley (Lützeroda)
- Type: Complete closure
- Duration: until 27.10.2023
- Reason : Civil engineering works (sewage; drinking water)
- Details: A detour will be signposted on site.
ANNOUNCEMENT
Wöllnitz
- Type: Temporary half-side closure + sidewalk closure
- Duration: 15.05.2023 to 30.09.2023
- Reason: Civil engineering work for laying fiber optic cable
- Details: The construction site can be passed safely on foot
Ziegenhain
- Type: Temporary half-side closure + footpath closure
- Duration: 22.05.2023 to 17.07.2023
- Reason: Civil engineering work for laying fiber optic cable
- Details: The construction site can be passed safely on foot.