The construction site report for week 25 (19 - 25.06.2023)

16.06.2023

Here is the current roadworks report for the 25th calendar week (19 - 25.06.2023).

Unless otherwise stated, you can walk or cycle past the roadworks.

FINISHED CONSTRUCTION SITES

Jenzigweg

  • Sewer connections have been made.

32nd Jena Paradise Triathlon

  • Event is finished.

Laasan

  • Fiber optic cable expansion is completed.

Lessingstrasse

  • Pavement renovation has been completed.

NEW CONSTRUCTION SITES / CLOSURES

Football tournament Saale-Cup

  • Type: Traffic obstructions
  • Location: Oberaue
  • Duration: 23.06.2023 to 25.06.2023
  • Reason: Event
  • Details: Due to the high number of participants, there may be traffic obstructions in the surrounding area.

Philosophenweg

  • Type: Complete closure
  • Location: House number 28
  • Duration: 19.06.2023 to 23.06.2023
  • Reason: Civil engineering works
  • Details: Road users can reach Philosophenweg via the other exit. The construction site can be passed safely on foot.

EXISTING ROADWORKS

2x Am Erlkönig

  • Type: Temporary closures of the verge and carriageway area
  • Duration: until 31.07.2023
  • Reason: Civil engineering work for laying fiber optic cables
  • Details: The cycle path connection in the direction of Kunitz remains passable, but special care is required due to partial closures in the edge and carriageway area of the cycle path.
  • Type: Complete closure
  • Location: up to the Talstein nursery
  • Duration: until approx. 10.11.2023
  • Reason: Development of the local heating network for the emerging "Erlenhöfe" residential area
  • Details: From 15.06.2023, the closure at the Gembdental/ Am Erlkönig/ Am Jenzig junction will be lifted. The detour to the gardens and the nursery will be via Kunitz. Access to the gardens parallel to the campsite (between Gembdenbach and Am Erlkönig) is not possible.

Buchenweg

  • Type: Half-sided closure
  • Location: House number 34
  • Duration: until 30.07.2023
  • Reason: Construction site installation for the conversion of the adjacent school
  • Details: Waiting is compulsory for vehicles meeting in the carriageway area.

Damaschkeweg

  • Type: Complete closure
  • Location: At house number 55
  • Duration: until 14.07.2023
  • Reason: Sewer construction work
  • Details: The construction site can be passed safely on foot.

Dammstraße

  • Location: Magnus-Poser-Straße to Schenkstraße (1st construction phase)
  • Type: Complete closure
  • Duration: until 30.05.2024
  • Reason: Line and traffic system renewal
  • Details: The construction work is divided into two construction phases. Pedestrians can pass the construction site safely. A detour for private traffic will be signposted on site.
  • 1st construction phase: Magnus-Poser-Straße to Schenkstraße
  • 2nd construction phase: Schenkstraße to Charlottenstraße

Drackendorf

  • Type: Temporary restrictions
  • Duration: until 30.06.2022
  • Reason: Civil engineering work for laying fiber optic cables

Erlanger Allee - cycle path connection between Lobeda-Ost and Lobeda-West

  • Type: Closure of partial areas and path connections
  • Location: between Theobald-Renner-Str. and Kastanienstraße junction and in the opposite direction
  • Duration: until 29.02.2024
  • Reason: Construction of a cycle path connection
  • Details: In the first construction phase, the roadway will be closed on one side and the pedestrian crossing at Platanenstraße to Paul-Schneider-Straße will be fully closed.
  • Attention: In the period 26 - 30 June 2023, the ramp to Lobeda West will be fully closed on 2 days in the direction out of town. During this time, the detour will be via Stadtrodaer Straße/Fritz-Ritter-Straße.

Ernst-Haeckel-Straße

  • Type: Complete closure
  • Duration: until 15.07.2023
  • Reason: Renewal of the sewer
  • Details: Traffic will be diverted via Knebelstraße/ Am Eisenbahndamm or via Magdelstieg/ Tatzendpromenade.

Friedrich-Engels-Straße

  • Type: Complete closure
  • Location: House number 38
  • Reason: Accident
  • Details: As it is not yet possible to foresee what damage has been caused to the underground pipes or the road, it is not yet possible to announce the end of the works. Bus traffic will be diverted via Burgweg/Ziegenhainer Straße. Smaller buses will be used. In the direction of the city center, buses will run via Kernbergstraße/ Am Kochersgraben.

Sidewalk closure from Lutherplatz/ corner Saalbahnhofstraße to Dornburger Str. 52

  • Duration: until 14.07.2023
  • Reason: Installation/conversion of catenary masts
  • Details: For the most part, pedestrians can pass the construction site safely. If the pavement is completely closed, pedestrians and cyclists will be diverted accordingly. The construction work will begin on 02.05.2023 at Lutherplatz / corner of Saalbahnhofstraße and end on 14.07.2023 at Dornburger Straße 52.

Julius-Schaxel-Straße

  • Type: Complete closure
  • Duration: until 31.08.2023
  • Reason: Road expansion incl. pipe laying
  • Details: The construction site can be passed on foot.

Kunitz

  • Type: Temporary restrictions
  • Duration: until 14.07.2023 (expected)
  • Reason: Continuation of civil engineering work for fiber optic expansion
  • Details: There will be restrictions in the areas of Laasaner Oberweg, Blumenröschenweg, Unter dem Heuhm, Hinter dem Spielberge, Am Mönchsberge, Am Wiesenbach and Am Spielberg.

Lobeda East and Illmnitz

  • Type: Temporary half-side closure + sidewalk closure
  • Duration: until 30.09.2023
  • Reason: Civil engineering work for laying fiber optic cable
  • Details: The construction site can be passed safely on foot.

Lützeroda

  • Type: Temporary restrictions
  • Duration: until 17.07.2023
  • Reason: Civil engineering work for the laying of fiber optic cables

Magdelstieg

  • Type: Complete closure
  • Location: between house numbers 143 and 151
  • Duration: until 23.06.2023, in the time from 8:00 - 17:30
  • Reason: Replacement of the drinking water pipe
  • Details: The construction site can be passed safely on foot and by bike

2x Oberaue

  • Type: Complete closure
  • Location: From the Saaleeingang Ernst-Abbe-Sportfeld entrance to just before the Lichtenhainer Brücke bridge
  • Duration: until 30.07.2023
  • Reason: Work on the stadium grandstand
  • Details: The Lichtenhain Bridge is not affected by the closure. A detour for pedestrians and cyclists is signposted.
  • Type: Closure of partial areas
  • Location: From the main stadium access road to Roland-Ducke-Weg
  • Duration: until 04.08.2023
  • Reason: Expansion of the road and ancillary facilities
  • Details: Access to the Oberaue will always be possible. In the first construction phase, work is currently underway from the main stadium access road to just before the Roland-Ducke-Weg junction. The construction site can be passed, but obstructions are to be expected. Cyclists can bypass the construction site safely and quickly. A detour has been set up and signposted for this purpose.
  • In the 2nd construction phase from 24.04.2023, the main access road to the stadium will be closed on one side. Traffic will be guided alternately by a mobile traffic light system.

Schloßgasse

  • Type: Complete closure
  • Location: Main entrance to the university up to the junction with Saalstraße
  • Duration: until 31.08.2023
  • Reason: Renewal of the sewer
  • Details: The construction site can be passed safely on foot.

Thomas-Münzer-Weg

  • Type: Complete closure
  • Location: House number 4
  • Duration: until 30.06.2023
  • Reason: Construction of a residential building
  • Details: The full closure is indicated by means of planning boards from both Jägerbergstraße and Max-Gräfe-Gasse. The restricted area must be driven around extensively. The construction site can be safely passed on foot and by bike

Wöllnitz

  • Type: Temporary half-side closure + sidewalk closure
  • Duration: until 30.09.2023
  • Reason: Civil engineering work for laying fiber optic cables
  • Details: The construction site can be passed safely on foot.

To the Ziskauer valley (Lützeroda)

  • Type: Complete closure
  • Duration: until 27.10.2023
  • Reason: Civil engineering works (sewage; drinking water)
  • Details: A detour will be signposted on site.

ANNOUNCEMENT

Am Anger

  • Type: Full closure of lanes
  • Location: House number 30-32
  • Duration: 26.06.2023 to 01.09.2023
  • Reason: Work on the drinking water pipeline
  • Details: There will be lane swings so that you can drive safely in and out of the city.