Dummy link to fix Firefox-Bug: First child with tabindex is ignored

Soil investigations at Eichplatz from April

26.03.2021

The ground investigation on the first construction site of the Eichplatz area will begin in mid-April. There will be an on-site meeting at the end of March to coordinate and mark the drilling points. The actual drilling is planned from mid-April and will take around 4 weeks. During this period, Eichplatz will have to be partially closed.

The contracted company is required to keep disruption to local residents to a minimum and to carry out the work during the legally stipulated times of day. Information, including the exact start of drilling, will be available on the project website www.eichplatzareal.de.